Causes of Contractual Conflicts in CPEC Project - Two Case Studies

China-Pakistan Economic Corridor (CPEC) is considered a game changer for the continent of Asia, Pakistan especially. China has invested around US$ 62 Billion in the fully operational corridor. Contractual conflicts are a significant source of delay in CPEC projects. Contractual conflicts are mostly because of poor financial and management control over it. In this paper, we have discussed the types of contractual conflicts that occur in projects that cause delays and the approaches that will help minimize the conflicts for the smooth occurrence of projects. For this purpose, a questionnaire was prepared and distributed to the major stakeholders of the projects. Secondly, the contractual conflicts are discussed based on the Pakistan literature review and compared with those of other countries. Two case studies were conducted to examine its causes: (1) political involvement and legal issues, (2) procurement and contract management, and (3) land acquisition problems

Authors

Institutions

Publication Details

Journal
Construction technologies and architecture
Published
2025-01-10
DOI
https://doi.org/10.4028/p-n2ql7p
Primary Topic
Belt and Road Initiative
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Causes of Contractual Conflicts in CPEC Project - Two Case Studies

Muhammad Jawad, Fahad Aslam, Abdul Hanan, Abdullah Abdullah et al.
Construction technologies and architecture
Belt and Road Initiative
article

Causes of Contractual Conflicts in CPEC Project - Two Case Studies

Muhammad Jawad, Fahad Aslam, Abdul Hanan, Abdullah Abdullah, Inaya Mahnoor
article en

Abstract

China-Pakistan Economic Corridor (CPEC) is considered a game changer for the continent of Asia, Pakistan especially. China has invested around US$ 62 Billion in the fully operational corridor. Contractual conflicts are a significant source of delay in CPEC projects. Contractual conflicts are mostly because of poor financial and management control over it. In this paper, we have discussed the types of contractual conflicts that occur in projects that cause delays and the approaches that will help minimize the conflicts for the smooth occurrence of projects. For this purpose, a questionnaire was prepared and distributed to the major stakeholders of the projects. Secondly, the contractual conflicts are discussed based on the Pakistan literature review and compared with those of other countries. Two case studies were conducted to examine its causes: (1) political involvement and legal issues, (2) procurement and contract management, and (3) land acquisition problems

Construction technologies and architectureVol. 15
University of Engineering and Technology Lahore (PK)
No poverty
Openalex Percentile: Top 99%
Belt and Road Initiative
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Causes of Contractual Conflicts in CPEC Project - Two Case Studies — Muhammad Jawad, Fahad Aslam, et al. · Construction technologies and architecture (2025) | TGRS Research Map | TGRS