Multiobjective Ant Colony System Algorithm for Component-Level Construction Schedule Optimization

Automatic generation of construction schedules has emerged as a key solution to address the inefficiencies and instabilities arising from the over-reliance on empirical judgment. However, traditional construction scheduling has been predominantly limited to regional levels, inadequately addressing the lean construction requirements of component-based prefabricated steel frame (PSF) structures. To bridge this gap, this study formulates an optimization model for the component-level resource-constrained project scheduling problem for PSF structures (C-RCPSP-PSF), which realizes the automatic extraction of precedence relationships from building information modeling three-dimensional (BIM 3D) models and the minimization of construction duration, costs, and carbon emissions. To address the C-RCPSP-PSF model, a novel multiobjective ant colony system (MOACS) algorithm is developed that utilizes three distinct colonies to individually tackle the objectives and combines taboo lists and global archives to enhance the search. Experimental results show the superior convergence and diversity of the MOACS over that of other competitive multiobjective optimization algorithms in solving the proposed model.

Authors

Institutions

Publication Details

Journal
Journal of Construction Engineering and Management
Published
2025-01-09
DOI
https://doi.org/10.1061/jcemd4.coeng-15827
Citations
2
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
4.21
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Multiobjective Ant Colony System Algorithm for Component-Level Construction Schedule Optimization

Jie Wu, Zhaozheng Shen
2 citations
Journal of Construction Engineering and Management
Resource-Constrained Project Scheduling
4.21
article

Multiobjective Ant Colony System Algorithm for Component-Level Construction Schedule Optimization

Jie Wu, Zhaozheng Shen
article en
2 citations

Abstract

Automatic generation of construction schedules has emerged as a key solution to address the inefficiencies and instabilities arising from the over-reliance on empirical judgment. However, traditional construction scheduling has been predominantly limited to regional levels, inadequately addressing the lean construction requirements of component-based prefabricated steel frame (PSF) structures. To bridge this gap, this study formulates an optimization model for the component-level resource-constrained project scheduling problem for PSF structures (C-RCPSP-PSF), which realizes the automatic extraction of precedence relationships from building information modeling three-dimensional (BIM 3D) models and the minimization of construction duration, costs, and carbon emissions. To address the C-RCPSP-PSF model, a novel multiobjective ant colony system (MOACS) algorithm is developed that utilizes three distinct colonies to individually tackle the objectives and combines taboo lists and global archives to enhance the search. Experimental results show the superior convergence and diversity of the MOACS over that of other competitive multiobjective optimization algorithms in solving the proposed model.

Journal of Construction Engineering and ManagementVol. 151(3)
Tongji University (CN)
Openalex Percentile: Top 8%
Resource-Constrained Project Scheduling
4.21
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.