Network-wide mixed-rail traffic scheduler: challenges and implementation aspects

In 2020, Indian Railways took up a de novo timetabling exercise for the Golden Quadrilateral and Diagonals (GQD) connecting Mumbai-Delhi-Kolkata-Chennai, involving about 1700 trains on a weekly basis over a network of 9,099 km. Based on significant participation in this activity, this paper elaborates on the challenges faced in a network-wide simulation and scheduling of trains across a large network. The methods to address these challenges and the software implementation aspects are also described. A network-wide mixed-rail traffic simulator was used successfully to construct a daily timetable for the GQD. The two primary goals of the Zero Based Timetabling (ZBTT) project were to generate train schedules that were: (a) feasible (in terms of kinematic constraints on both trains running and block-section, running lines) and (b) conflict-free (due to multiple trains having to share resources and the need to ensure time-durations of resource usage are different, subject to safety constraints), for a proposed set of departure timings and halt patterns of all the services that were planned on the GQD.

Authors

Institutions

Publication Details

Journal
Transportation research procedia
Published
2025-01-01
DOI
https://doi.org/10.1016/j.trpro.2024.12.193
Primary Topic
Railway Systems and Energy Efficiency
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Network-wide mixed-rail traffic scheduler: challenges and implementation aspects

Madhu N. Belur, Sudarshan Pulapadi, Merajus Salekin, Narayan Rangaraj et al.
Transportation research procedia
Railway Systems and Energy Efficiency
article

Network-wide mixed-rail traffic scheduler: challenges and implementation aspects

Madhu N. Belur, Sudarshan Pulapadi, Merajus Salekin, Narayan Rangaraj, Karim Shahbaz, Samay P. Singh, Raja Gopalakrishnan, Mayurika S Tyagi, Sidhartha I Kumar, Satwik V. Ramisetty
article en

Abstract

In 2020, Indian Railways took up a de novo timetabling exercise for the Golden Quadrilateral and Diagonals (GQD) connecting Mumbai-Delhi-Kolkata-Chennai, involving about 1700 trains on a weekly basis over a network of 9,099 km. Based on significant participation in this activity, this paper elaborates on the challenges faced in a network-wide simulation and scheduling of trains across a large network. The methods to address these challenges and the software implementation aspects are also described. A network-wide mixed-rail traffic simulator was used successfully to construct a daily timetable for the GQD. The two primary goals of the Zero Based Timetabling (ZBTT) project were to generate train schedules that were: (a) feasible (in terms of kinematic constraints on both trains running and block-section, running lines) and (b) conflict-free (due to multiple trains having to share resources and the need to ensure time-durations of resource usage are different, subject to safety constraints), for a proposed set of departure timings and halt patterns of all the services that were planned on the GQD.

Transportation research procediaVol. 82
Indian Institute of Technology Bombay (IN)
Openalex Percentile: Top 100%
Railway Systems and Energy Efficiency
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.