Fixed start method for repetitive project scheduling with simulated annealing

This research deals with the high project completion variability by presenting a new method to decrease such variability in repetitive construction projects. To achieve this, a Fixed Start Method (FSM) -where the starts of each activity with a high level of probabilistic confidence for the planned project duration are fixed- was applied, where the high level of probabilistic confidence obtained was optimized with the use of the metaheuristic algorithm called Simulated Annealing (SA). This procedure evaluated the project completion in a case study based on the coefficient of variance (COV) of the resulting standard deviation, mean, and temperature selected for the SA. Thus, the combined FSM and SA (FSSA) is a new method that decreases the variability of scheduling duration while achieving project completion times. Finally, the proposed FSSA method for construction scheduling was validated in a case study using Discrete Event Simulation.

Authors

Institutions

Publication Details

Journal
Heliyon
Published
2025-01-01
DOI
https://doi.org/10.1016/j.heliyon.2025.e41741
Citations
5
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
5.03

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Fixed start method for repetitive project scheduling with simulated annealing

Felipe Baesler, Eric Forcael, Francisco Orozco, Duzgun Agdas et al.
5 citations
Heliyon
BIM and Construction Integration
5.03
article

Fixed start method for repetitive project scheduling with simulated annealing

Felipe Baesler, Eric Forcael, Francisco Orozco, Duzgun Agdas, Francisco Moreno
article en
5 citations

Abstract

This research deals with the high project completion variability by presenting a new method to decrease such variability in repetitive construction projects. To achieve this, a Fixed Start Method (FSM) -where the starts of each activity with a high level of probabilistic confidence for the planned project duration are fixed- was applied, where the high level of probabilistic confidence obtained was optimized with the use of the metaheuristic algorithm called Simulated Annealing (SA). This procedure evaluated the project completion in a case study based on the coefficient of variance (COV) of the resulting standard deviation, mean, and temperature selected for the SA. Thus, the combined FSM and SA (FSSA) is a new method that decreases the variability of scheduling duration while achieving project completion times. Finally, the proposed FSSA method for construction scheduling was validated in a case study using Discrete Event Simulation.

HeliyonVol. 11(2)
San Sebastián University (CL), University of Florida (US), Universidad Panamericana (GT), Universidad Panamericana (MX)
Universidad Panamericana
Openalex Percentile: Top 6%
BIM and Construction Integration
5.03
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Fixed start method for repetitive project scheduling with simulated annealing — Felipe Baesler, Eric Forcael, et al. · Heliyon (2025) | TGRS Research Map | TGRS