Fixed start method for repetitive project scheduling with simulated annealing
This research deals with the high project completion variability by presenting a new method to decrease such variability in repetitive construction projects. To achieve this, a Fixed Start Method (FSM) -where the starts of each activity with a high level of probabilistic confidence for the planned project duration are fixed- was applied, where the high level of probabilistic confidence obtained was optimized with the use of the metaheuristic algorithm called Simulated Annealing (SA). This procedure evaluated the project completion in a case study based on the coefficient of variance (COV) of the resulting standard deviation, mean, and temperature selected for the SA. Thus, the combined FSM and SA (FSSA) is a new method that decreases the variability of scheduling duration while achieving project completion times. Finally, the proposed FSSA method for construction scheduling was validated in a case study using Discrete Event Simulation.
Authors
- Felipe Baesler (ORCID: https://orcid.org/0000-0002-5231-6803)
- Eric Forcael (ORCID: https://orcid.org/0000-0002-3036-4329)
- Francisco Orozco (ORCID: https://orcid.org/0000-0003-2409-1026)
- Duzgun Agdas (ORCID: https://orcid.org/0000-0002-3703-914X)
- Francisco Moreno (ORCID: https://orcid.org/0000-0003-4058-9350)
Institutions
- San Sebastián University (CL)
- University of Florida (US)
- Universidad Panamericana (GT)
- Universidad Panamericana (MX)
Publication Details
- Journal
- Heliyon
- Published
- 2025-01-01
- DOI
- https://doi.org/10.1016/j.heliyon.2025.e41741
- Citations
- 5
- Primary Topic
- BIM and Construction Integration
- Type
- article
- Field-Weighted Citation Impact
- 5.03
Funders
- Universidad Panamericana