Utilizing arithmetic optimization algorithm for optimizing time and cost in construction project

The time-cost trade-off problem (TCTP) presents a significant challenge in construction management, requiring a balance between project duration and associated costs for successful completion.This study evaluates the performance of an arithmetic optimization algorithm (AOA) for solving the TCTP.AOA integrates non-dominated sorting (NDS) to generate Pareto-optimal solutions that address both time and cost objectives.The methodology involves testing the AOA on three case studies representing small-and medium-scale construction projects with 18, 29, and 63 activities.Comparative analyses with traditional metaheuristic algorithms, such as ant colony optimization, genetic algorithms, and particle optimization algorithms, reveal that NDS-AOA delivers competitive results, particularly in smaller projects, that achieve lower costs and faster computation times.However, its effectiveness decreases in medium-scale projects, indicating scalability limitations.Numerical tests suggest that while AOA is wellsuited for small to medium projects, it requires further enhancements, such as hybridization with other techniques, to effectively handle larger-scale problems.

Authors

Publication Details

Journal
Journal of Construction Engineering Management & Innovation
Published
2024-12-30
DOI
https://doi.org/10.31462/jcemi.2024.04336353
Citations
3
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.80
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Utilizing arithmetic optimization algorithm for optimizing time and cost in construction project

Vedat Toğan, Fatemeh Mostofi, Abdikarim Said Sulub
3 citations
Journal of Construction Engineering Management & Innovation
BIM and Construction Integration
0.80
article

Utilizing arithmetic optimization algorithm for optimizing time and cost in construction project

Vedat Toğan, Fatemeh Mostofi, Abdikarim Said Sulub
article en
3 citations

Abstract

The time-cost trade-off problem (TCTP) presents a significant challenge in construction management, requiring a balance between project duration and associated costs for successful completion.This study evaluates the performance of an arithmetic optimization algorithm (AOA) for solving the TCTP.AOA integrates non-dominated sorting (NDS) to generate Pareto-optimal solutions that address both time and cost objectives.The methodology involves testing the AOA on three case studies representing small-and medium-scale construction projects with 18, 29, and 63 activities.Comparative analyses with traditional metaheuristic algorithms, such as ant colony optimization, genetic algorithms, and particle optimization algorithms, reveal that NDS-AOA delivers competitive results, particularly in smaller projects, that achieve lower costs and faster computation times.However, its effectiveness decreases in medium-scale projects, indicating scalability limitations.Numerical tests suggest that while AOA is wellsuited for small to medium projects, it requires further enhancements, such as hybridization with other techniques, to effectively handle larger-scale problems.

Journal of Construction Engineering Management & InnovationVol. 7(4)
Sustainable cities and communities
Openalex Percentile: Top 27%
BIM and Construction Integration
0.80
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.