An algorithmic review of the technological progress and milestones in resource-constrained project planning

Engineering, procurement, and construction projects are time-intensive and subject to resource constraints. Modern project planning software requires optimization algorithms to schedule tasks while considering resource availability. A comprehensive review of the optimization algorithms used in project planning has not yet been conducted. This study seeks to bridge the gap through an algorithmic review of the Resource-constrained Project Scheduling Problems (RCPSPs) literature and investigates the following research questions: What are the milestones on the main development trajectory of optimization algorithms for solving RCPSPs? How might this influence future advancements in the field? To answer these questions, the Main Path Analysis (MPA) method is employed to review the development trajectory and milestones from over 1100 project scheduling articles published between 1980 and 2024. Cluster Analysis (CA) complements the investigations by identifying the prevalent research themes, mathematical features, and solution algorithms. Recommendations for future research directions, supported by the systematic review, conclude the study. This review provides a reference for project management researchers focused on industrial applications of project scheduling problems.

Authors

Publication Details

Journal
Advances in Production Engineering & Management
Published
2024-12-29
DOI
https://doi.org/10.14743/apem2024.4.520
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

An algorithmic review of the technological progress and milestones in resource-constrained project planning

Pourya Pourhejazy, Kuo‐Ching Ying, Chen-Yang Cheng
Advances in Production Engineering & Management
BIM and Construction Integration
article

An algorithmic review of the technological progress and milestones in resource-constrained project planning

Pourya Pourhejazy, Kuo‐Ching Ying, Chen-Yang Cheng
article en

Abstract

Engineering, procurement, and construction projects are time-intensive and subject to resource constraints. Modern project planning software requires optimization algorithms to schedule tasks while considering resource availability. A comprehensive review of the optimization algorithms used in project planning has not yet been conducted. This study seeks to bridge the gap through an algorithmic review of the Resource-constrained Project Scheduling Problems (RCPSPs) literature and investigates the following research questions: What are the milestones on the main development trajectory of optimization algorithms for solving RCPSPs? How might this influence future advancements in the field? To answer these questions, the Main Path Analysis (MPA) method is employed to review the development trajectory and milestones from over 1100 project scheduling articles published between 1980 and 2024. Cluster Analysis (CA) complements the investigations by identifying the prevalent research themes, mathematical features, and solution algorithms. Recommendations for future research directions, supported by the systematic review, conclude the study. This review provides a reference for project management researchers focused on industrial applications of project scheduling problems.

Advances in Production Engineering & ManagementVol. 19(4)
Industry, innovation and infrastructure
Openalex Percentile: Top 73%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

An algorithmic review of the technological progress and milestones in resource-constrained project planning — Pourya Pourhejazy, Kuo‐Ching Ying, et al. · Advances in Production Engineering & Management (2024) | TGRS Research Map | TGRS