Penjadwalan Waktu Proyek Pembangunan Tempat Gym Menggunakan Metode CPM (Critical Path Method)

Project scheduling is a method of arranging a schedule of tasks to be carried out to realize or achieve certain goals, by filling in a table of the time needed to complete. Critical Part Method (CPM) is a program method that can calculate the time needed to complete all activities and determine which ones the project implementer should pay attention to to ensure they can be completed as planned. The purpose of this study is to identify the critical path to which critical activities are included, as well as evaluate the scheduling between the project owner's planned time and the duration of the planning outcome. In the construction project of a gym with a land area of 60m (5 x 12m) in Mustika Prakarsa Block C Housing, Cibalongsari Village, Klari District, Karawang Regency, 41371. The data collected from this study is research analysis shows that fast and normal time network lines A, B, C, D, F, I, J, K, L, activities include making water channels, digging foundations, installing foundations, ironing, laying hebel bricks, polishing, installing floor tiles, checking, overall finishing. So, the project scheduling time based on the CPM method is 124 days normal time and 91 days fast time to complete the project. Keywords: Critical Path Method, Project Development, Project Management, Scheduling.

Authors

Institutions

Publication Details

Journal
Industrika Jurnal Ilmiah Teknik Industri
Published
2024-10-16
DOI
https://doi.org/10.37090/indstrk.v8i4.1466
Citations
1
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.55
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Penjadwalan Waktu Proyek Pembangunan Tempat Gym Menggunakan Metode CPM (Critical Path Method)

Sutrisno Sutrisno, Nabila Zahra, Novita Yuliani
1 citations
Industrika Jurnal Ilmiah Teknik Industri
Management and Optimization Techniques
0.55
article

Penjadwalan Waktu Proyek Pembangunan Tempat Gym Menggunakan Metode CPM (Critical Path Method)

Sutrisno Sutrisno, Nabila Zahra, Novita Yuliani
article en
1 citations

Abstract

Project scheduling is a method of arranging a schedule of tasks to be carried out to realize or achieve certain goals, by filling in a table of the time needed to complete. Critical Part Method (CPM) is a program method that can calculate the time needed to complete all activities and determine which ones the project implementer should pay attention to to ensure they can be completed as planned. The purpose of this study is to identify the critical path to which critical activities are included, as well as evaluate the scheduling between the project owner's planned time and the duration of the planning outcome. In the construction project of a gym with a land area of 60m (5 x 12m) in Mustika Prakarsa Block C Housing, Cibalongsari Village, Klari District, Karawang Regency, 41371. The data collected from this study is research analysis shows that fast and normal time network lines A, B, C, D, F, I, J, K, L, activities include making water channels, digging foundations, installing foundations, ironing, laying hebel bricks, polishing, installing floor tiles, checking, overall finishing. So, the project scheduling time based on the CPM method is 124 days normal time and 91 days fast time to complete the project. Keywords: Critical Path Method, Project Development, Project Management, Scheduling.

Industrika Jurnal Ilmiah Teknik IndustriVol. 8(4)
University of Singaperbangsa Karawang (ID)
Sustainable cities and communities
Openalex Percentile: Top 19%
Management and Optimization Techniques
0.55
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.