The Impact of Schedule Compression Techniques on Construction Project Timelines: A Case Study in Basrah, Iraq

Introduction Project managers always compete to finish their projects on time. However, certain circumstances force them to use schedule compression techniques - such as activity crashing, overlapping, and method substitution, to address unplanned delays. Methods These techniques offer practical means to accelerate project timelines; however, their degree of effectiveness can vary widely across different projects and contexts. Nevertheless, such circumstances make compressing construction project schedules an important consideration for avoiding financial losses and protecting stakeholders' interests. Results The paper aims to evaluate the effect of schedule compression techniques on a construction project located in one of Basrah’s oil fields in Iraq. A case study approach is followed for discussing time-cost trade-offs, challenges, and outcomes with such techniques, including their financial implications, strategies for mitigating risks, and the management of resources. Conclusion The results provide insights that are useful in the optimisation of project schedules while ensuring that constraints for cost, safety, and operation are met.

Authors

Institutions

Publication Details

Journal
The Open Civil Engineering Journal
Published
2024-12-27
DOI
https://doi.org/10.2174/0118741495360335241205110710
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

The Impact of Schedule Compression Techniques on Construction Project Timelines: A Case Study in Basrah, Iraq

Khaldoon Shehab Al-Tameemi
The Open Civil Engineering Journal
BIM and Construction Integration
article

The Impact of Schedule Compression Techniques on Construction Project Timelines: A Case Study in Basrah, Iraq

Khaldoon Shehab Al-Tameemi
article en

Abstract

Introduction Project managers always compete to finish their projects on time. However, certain circumstances force them to use schedule compression techniques - such as activity crashing, overlapping, and method substitution, to address unplanned delays. Methods These techniques offer practical means to accelerate project timelines; however, their degree of effectiveness can vary widely across different projects and contexts. Nevertheless, such circumstances make compressing construction project schedules an important consideration for avoiding financial losses and protecting stakeholders' interests. Results The paper aims to evaluate the effect of schedule compression techniques on a construction project located in one of Basrah’s oil fields in Iraq. A case study approach is followed for discussing time-cost trade-offs, challenges, and outcomes with such techniques, including their financial implications, strategies for mitigating risks, and the management of resources. Conclusion The results provide insights that are useful in the optimisation of project schedules while ensuring that constraints for cost, safety, and operation are met.

The Open Civil Engineering JournalVol. 19(1)
University of Basrah (IQ)
Openalex Percentile: Top 74%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

The Impact of Schedule Compression Techniques on Construction Project Timelines: A Case Study in Basrah, Iraq — Khaldoon Shehab Al-Tameemi · The Open Civil Engineering Journal (2024) | TGRS Research Map | TGRS