Timing Optimization Method for Pumped Storage Plant Construction Considering Capital Expenditure Capacity Feedback

With the extensive integration of renewable energy into the power grid, pumped storage power plants have become an essential component in the development of modern power systems due to their rapid response capabilities, advanced technology, and other beneficial features. However, high construction costs and irrational capital expenditure and construction schedules have constrained the robust and sustainable growth of pumped storage plants. Therefore, this paper proposes a pumped storage plant construction timing optimization method considering capital expenditure capacity feedback. Initially, an analysis is conducted on the factors that influence the capital expenditure costs of pumped storage power plants throughout their lifecycle. Next, the value of investing in pumped storage plants is assessed across three different aspects: economics, environment, and reliability. Finally, according to the principle of dynamic planning combined with the actual needs and capital expenditure potential of pumped storage plants, the sum of the capital expenditure effectiveness values in each stage is used as the indicator function of each stage to construct the pumped storage plants project capital expenditure timing optimization model, and a simulation analysis is carried out with Province Z as an example to verify the validity and applicability of the proposed model. The findings indicate that the suggested model is effective in balancing the implementation time of individual projects to achieve the maximum cumulative capital expenditure performance over the entire planning period.

Authors

Institutions

Publication Details

Journal
Energies
Published
2024-12-27
DOI
https://doi.org/10.3390/en18010047
Citations
1
Primary Topic
Integrated Energy Systems Optimization
Type
article
Field-Weighted Citation Impact
0.21

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Timing Optimization Method for Pumped Storage Plant Construction Considering Capital Expenditure Capacity Feedback

Wenshi Ren, Jie Jiao, Xiaxin Lei, Guangxiu Yu et al.
1 citations
Energies
Integrated Energy Systems Optimization
0.21
article

Timing Optimization Method for Pumped Storage Plant Construction Considering Capital Expenditure Capacity Feedback

Wenshi Ren, Jie Jiao, Xiaxin Lei, Guangxiu Yu, Qian Wang, Qi Shi, Puyu He
article en
1 citations

Abstract

With the extensive integration of renewable energy into the power grid, pumped storage power plants have become an essential component in the development of modern power systems due to their rapid response capabilities, advanced technology, and other beneficial features. However, high construction costs and irrational capital expenditure and construction schedules have constrained the robust and sustainable growth of pumped storage plants. Therefore, this paper proposes a pumped storage plant construction timing optimization method considering capital expenditure capacity feedback. Initially, an analysis is conducted on the factors that influence the capital expenditure costs of pumped storage power plants throughout their lifecycle. Next, the value of investing in pumped storage plants is assessed across three different aspects: economics, environment, and reliability. Finally, according to the principle of dynamic planning combined with the actual needs and capital expenditure potential of pumped storage plants, the sum of the capital expenditure effectiveness values in each stage is used as the indicator function of each stage to construct the pumped storage plants project capital expenditure timing optimization model, and a simulation analysis is carried out with Province Z as an example to verify the validity and applicability of the proposed model. The findings indicate that the suggested model is effective in balancing the implementation time of individual projects to achieve the maximum cumulative capital expenditure performance over the entire planning period.

EnergiesVol. 18(1)
North China Electric Power University (CN), State Grid Corporation of China (China) (CN)
Economic Research Institute, State Grid Sichuan Economic Research Institute, State Grid Corporation of China
Industry, innovation and infrastructure
Openalex Percentile: Top 45%
Integrated Energy Systems Optimization
0.21
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.