Behavior during Twin Tunnel Construction Based on Measurement Results and Validity of Numerical Analysis

In recent years, there has been an increase in cases where new tunnels are excavated parallel to existing tunnels along highways and major national roads. Although separation distances are secured in the planning and design phases to avoid interference between the tunnels, there can still be impacts on existing tunnels in poor ground conditions. In areas with poor ground stability, the excavation of a new tunnel can still lead to unanticipated impacts on the structural integrity of nearby, pre-existing tunnels. Previous research has documented measurement results and numerical analyses of factors such as existing tunnel lining stress and the behavior of the intermediate ground. However, few studies have sufficiently compared and discussed measurement results after the completion of new tunnel excavation with predicted analysis results. This study aims to analyze measurement data from an actual parallel tunnel construction project and examine the behavior of both the existing and new tunnels through numerical back-analyses based on these measurements, assessing the validity of these numerical predictions. From the measurements of ground displacement, lining stress, and crack displacement in the existing tunnel, it was observed that the loosening loads initially acting during the excavation of the existing tunnel were reactivated by the excavation of the new tunnel, indicating the effects of close-proximity construction. The back-analysis results showed discrepancies between measured and predicted values of crown settlement and inner displacement when using a standard stress release rate for the ground properties and lateral earth pressure coefficient of the existing tunnel in the new tunnel excavation analysis. Adjusting the stress release rate brought the displacement predictions closer to the measured values, and aligning the displacements allowed the lining stress to be reasonably predicted. Consequently, this approach to back-analysis demonstrates that it is possible to estimate the impact on the existing tunnel during new tunnel excavation.

Authors

Institutions

Publication Details

Journal
Journal of MMIJ
Published
2024-12-26
DOI
https://doi.org/10.2473/journalofmmij.mmij-2024-004
Primary Topic
Geotechnical Engineering and Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Behavior during Twin Tunnel Construction Based on Measurement Results and Validity of Numerical Analysis

Koichi Aoki, Yujing Jiang, Qiwei Lin, Hitoshi Tezuka
Journal of MMIJ
Geotechnical Engineering and Analysis
article

Behavior during Twin Tunnel Construction Based on Measurement Results and Validity of Numerical Analysis

Koichi Aoki, Yujing Jiang, Qiwei Lin, Hitoshi Tezuka
article en

Abstract

In recent years, there has been an increase in cases where new tunnels are excavated parallel to existing tunnels along highways and major national roads. Although separation distances are secured in the planning and design phases to avoid interference between the tunnels, there can still be impacts on existing tunnels in poor ground conditions. In areas with poor ground stability, the excavation of a new tunnel can still lead to unanticipated impacts on the structural integrity of nearby, pre-existing tunnels. Previous research has documented measurement results and numerical analyses of factors such as existing tunnel lining stress and the behavior of the intermediate ground. However, few studies have sufficiently compared and discussed measurement results after the completion of new tunnel excavation with predicted analysis results. This study aims to analyze measurement data from an actual parallel tunnel construction project and examine the behavior of both the existing and new tunnels through numerical back-analyses based on these measurements, assessing the validity of these numerical predictions. From the measurements of ground displacement, lining stress, and crack displacement in the existing tunnel, it was observed that the loosening loads initially acting during the excavation of the existing tunnel were reactivated by the excavation of the new tunnel, indicating the effects of close-proximity construction. The back-analysis results showed discrepancies between measured and predicted values of crown settlement and inner displacement when using a standard stress release rate for the ground properties and lateral earth pressure coefficient of the existing tunnel in the new tunnel excavation analysis. Adjusting the stress release rate brought the displacement predictions closer to the measured values, and aligning the displacements allowed the lining stress to be reasonably predicted. Consequently, this approach to back-analysis demonstrates that it is possible to estimate the impact on the existing tunnel during new tunnel excavation.

Journal of MMIJVol. 140(12)
Nagasaki University (JP)
Sustainable cities and communities
Openalex Percentile: Top 70%
Geotechnical Engineering and Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.