ALGORITHM FOR CALCULATING RELIABILITY OF ON-SITE POWER SUPPLY SCHEMES USING CONNECTION COEFFICIENTS

The article deals with the method of simplifying the forecasting of reliability parameters and assessing the technical condition of the most critical nodes of the power supply system by means of connection coefficients. The aim of the study is to develop a methodology to determine the probability of failure-free operation of the power supply scheme using connection coefficients. Materials and methods. The scheme of 10/0,4 kV power supply within the workshop is presented. Probabilistic methods of reliability determination and mathematical statistics were used. Research results. The probability of failure-free operation in time using the exponential distribution law has been calculated. Graphs of dependences of probability of system uptime on the number of load connections, as well as graphs of changes in the values of connection coefficients in time are presented. The formulas for the load connection factors depending on the number of connections are derived. The received analytical expressions allow to model values at possible additional load connections. The obtained dependences allow to determine the probability of failure-free operation time of low-voltage electrical equipment, as well as the schemes of the in-house power supply. Conclusions. The proposed methodology simplifies the forecasting of reliability parameters of the scheme of the internal shop power supply and the assessment of the technical condition of the most important and critical nodes. The modeled values of the load connection coefficients can be used in technical and economic calculations, namely for further increase of the number of outgoing lines from the switchboard and distribution point or increase of the load on the line taking into account the permissible probability of failure-free operation of the scheme. The results of the study are recommended to evaluate technical performance and determination of the main reliability parameters of the operating systems of in-plant power supply.

Authors

Institutions

Publication Details

Journal
Vestnik Chuvashskogo universiteta
Published
2024-12-25
DOI
https://doi.org/10.47026/1810-1909-2024-4-117-127
Primary Topic
Power System Reliability and Maintenance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ALGORITHM FOR CALCULATING RELIABILITY OF ON-SITE POWER SUPPLY SCHEMES USING CONNECTION COEFFICIENTS

R. M. Petrova, Elena Gracheva
1 links
Vestnik Chuvashskogo universiteta
Power System Reliability and Maintenance
article

ALGORITHM FOR CALCULATING RELIABILITY OF ON-SITE POWER SUPPLY SCHEMES USING CONNECTION COEFFICIENTS

R. M. Petrova, Elena Gracheva
article en

Abstract

The article deals with the method of simplifying the forecasting of reliability parameters and assessing the technical condition of the most critical nodes of the power supply system by means of connection coefficients. The aim of the study is to develop a methodology to determine the probability of failure-free operation of the power supply scheme using connection coefficients. Materials and methods. The scheme of 10/0,4 kV power supply within the workshop is presented. Probabilistic methods of reliability determination and mathematical statistics were used. Research results. The probability of failure-free operation in time using the exponential distribution law has been calculated. Graphs of dependences of probability of system uptime on the number of load connections, as well as graphs of changes in the values of connection coefficients in time are presented. The formulas for the load connection factors depending on the number of connections are derived. The received analytical expressions allow to model values at possible additional load connections. The obtained dependences allow to determine the probability of failure-free operation time of low-voltage electrical equipment, as well as the schemes of the in-house power supply. Conclusions. The proposed methodology simplifies the forecasting of reliability parameters of the scheme of the internal shop power supply and the assessment of the technical condition of the most important and critical nodes. The modeled values of the load connection coefficients can be used in technical and economic calculations, namely for further increase of the number of outgoing lines from the switchboard and distribution point or increase of the load on the line taking into account the permissible probability of failure-free operation of the scheme. The results of the study are recommended to evaluate technical performance and determination of the main reliability parameters of the operating systems of in-plant power supply.

Vestnik Chuvashskogo universiteta(4)
Kazan State Power Engineering University (RU)
Openalex Percentile: Top 70%
Power System Reliability and Maintenance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ALGORITHM FOR CALCULATING RELIABILITY OF ON-SITE POWER SUPPLY SCHEMES USING CONNECTION COEFFICIENTS — R. M. Petrova, Elena Gracheva · Vestnik Chuvashskogo universiteta (2024) | TGRS Research Map | TGRS