Metaheuristic Multi-Objective Optimization Approach for Repetitive Construction Project Scheduling

The optimization of schedules for repetitive projects is a crucial phase in establishing an effective project timeline concerning both duration and cost. This study presents an innovative metaheuristic multi-objective optimization model tailored for repetitive projects. Distinguished by its original features, this model empowers schedulers to identify an optimal schedule that concurrently minimizes project duration, total cost, and interruption time. It encompasses various constraints and factors, including learning and forgetting effects, inter-activity soft logic, limited work interruption allowances, multiple crew formations, multiple construction methods per activity, while retaining all Critical Path Method (CPM) scheduling capabilities. The effectiveness of this new approach was validated through application to two case studies, demonstrating its capability to deliver optimal schedules for repetitive projects with heightened accuracy in minimizing project duration, cost, and interruption. Furthermore, the integration of learning effects, soft logic, and work interruption allowances within the optimization process substantially reduced project duration and cost, thereby yielding more precise and dependable optimal solutions.

Authors

Institutions

Publication Details

Journal
Adıyaman Üniversitesi Mühendislik Bilimleri Dergisi
Published
2024-12-25
DOI
https://doi.org/10.54365/adyumbd.1477358
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Metaheuristic Multi-Objective Optimization Approach for Repetitive Construction Project Scheduling

Gülçağ Albayrak
1 links
Adıyaman Üniversitesi Mühendislik Bilimleri Dergisi
Resource-Constrained Project Scheduling
article

Metaheuristic Multi-Objective Optimization Approach for Repetitive Construction Project Scheduling

Gülçağ Albayrak
article en

Abstract

The optimization of schedules for repetitive projects is a crucial phase in establishing an effective project timeline concerning both duration and cost. This study presents an innovative metaheuristic multi-objective optimization model tailored for repetitive projects. Distinguished by its original features, this model empowers schedulers to identify an optimal schedule that concurrently minimizes project duration, total cost, and interruption time. It encompasses various constraints and factors, including learning and forgetting effects, inter-activity soft logic, limited work interruption allowances, multiple crew formations, multiple construction methods per activity, while retaining all Critical Path Method (CPM) scheduling capabilities. The effectiveness of this new approach was validated through application to two case studies, demonstrating its capability to deliver optimal schedules for repetitive projects with heightened accuracy in minimizing project duration, cost, and interruption. Furthermore, the integration of learning effects, soft logic, and work interruption allowances within the optimization process substantially reduced project duration and cost, thereby yielding more precise and dependable optimal solutions.

Adıyaman Üniversitesi Mühendislik Bilimleri DergisiVol. 11(24)
Eskişehir Osmangazi University (TR)
Industry, innovation and infrastructure
Openalex Percentile: Top 70%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.