Improving predictions of the Estimate at Completion using the classic Earned Value input

The article investigates the author’s method of estimating the final cost of a construction investment. A list of proposed methods of calculating the value of the planned final cost of the EAC investment available in the world literature was used. The modification consisted in the first place in the verification and elimination of formulas that do not match the use in construction projects and the combination of formulas resulting in the same result. The study was aimed at enabling the right choice of the method of estimating the final cost of construction investments and determining the accuracy of this estimate. It should be emphasized that the analyzed investments were annexed many times during their implementation. On the basis of the obtained results of research carried out on real construction investments, it was found that 3 methods best predict the final cost of the investment. Finally, improvements were introduced, which were analyzed, the final effect of the article is a proposal of an original, universal formula, which in each of the analyzed construction investments, regardless of the trends, deviations from the cost at the time of the inspection, forecasts the most accurate result, consistent with reality. The conducted research gives the possibility of more effective financial management of a construction investment using the corrected EAC formula in EVM method.

Authors

Institutions

Publication Details

Journal
Archives of Civil Engineering
Published
2024-12-13
DOI
https://doi.org/10.24425/ace.2024.151892
Primary Topic
Construction Management and Sustainability
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Improving predictions of the Estimate at Completion using the classic Earned Value input

Anna Starczyk-Kołbyk
Archives of Civil Engineering
Construction Management and Sustainability
article

Improving predictions of the Estimate at Completion using the classic Earned Value input

Anna Starczyk-Kołbyk
article en

Abstract

The article investigates the author’s method of estimating the final cost of a construction investment. A list of proposed methods of calculating the value of the planned final cost of the EAC investment available in the world literature was used. The modification consisted in the first place in the verification and elimination of formulas that do not match the use in construction projects and the combination of formulas resulting in the same result. The study was aimed at enabling the right choice of the method of estimating the final cost of construction investments and determining the accuracy of this estimate. It should be emphasized that the analyzed investments were annexed many times during their implementation. On the basis of the obtained results of research carried out on real construction investments, it was found that 3 methods best predict the final cost of the investment. Finally, improvements were introduced, which were analyzed, the final effect of the article is a proposal of an original, universal formula, which in each of the analyzed construction investments, regardless of the trends, deviations from the cost at the time of the inspection, forecasts the most accurate result, consistent with reality. The conducted research gives the possibility of more effective financial management of a construction investment using the corrected EAC formula in EVM method.

Archives of Civil Engineering
Military University of Technology in Warsaw (PL)
Wojskowa Akademia Techniczna
Industry, innovation and infrastructure
Openalex Percentile: Top 74%
Construction Management and Sustainability
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Improving predictions of the Estimate at Completion using the classic Earned Value input — Anna Starczyk-Kołbyk · Archives of Civil Engineering (2024) | TGRS Research Map | TGRS