Exploring a recurrent neural network (RNN) earned value based model for predicting lost labour value in construction projects

This study explores the application of deep learning techniques in forecasting labour losses in construction projects. By leveraging the predictive capabilities of ManHour Earned and Estimated ManHour values, this research aims to develop an accurate and reliable model for labour loss forecasting. Utilizing a dataset comprising 105 work items from industry practitioners who employed the Leonard and Moselhi methodology, this study investigates the efficacy of a Recurrent Neural Network (RNN) architecture with Long Short-Term Memory (LSTM) cells. The model's performance is optimized through backpropagation and hyperparameter tuning, focusing on key parameters such as learning rate, batch size, dropout rate, and number of epochs. To ensure the model's generalizability and mitigate overfitting, regularization strategies and performance monitoring are employed. The predictive potential of the model is evaluated through integration into a real-time sequence production job and deployment into an enabled environment. Results demonstrate the model's capacity for accurate labour loss forecasting, enabling proactive measures to enhance productivity and minimize unnecessary claims. Although this study focuses on building projects, its findings have broader implications for process and manufacturing engineering, where productivity losses and associated labour losses are significant concerns. The practical application of this research lies in its potential to assess and counter labour loss claims, disputes, warrants, and demands in construction projects, ultimately contributing to improved project management and reduced financial losses.

Authors

Institutions

Publication Details

Journal
Discover Civil Engineering
Published
2024-12-20
DOI
https://doi.org/10.1007/s44290-024-00153-0
Citations
1
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.27
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Exploring a recurrent neural network (RNN) earned value based model for predicting lost labour value in construction projects

Samuel I. Egwunatum, Joel Oboshior, Opeyemi A. Osadola
1 citations
Discover Civil Engineering
BIM and Construction Integration
0.27
article

Exploring a recurrent neural network (RNN) earned value based model for predicting lost labour value in construction projects

Samuel I. Egwunatum, Joel Oboshior, Opeyemi A. Osadola
article en
1 citations

Abstract

This study explores the application of deep learning techniques in forecasting labour losses in construction projects. By leveraging the predictive capabilities of ManHour Earned and Estimated ManHour values, this research aims to develop an accurate and reliable model for labour loss forecasting. Utilizing a dataset comprising 105 work items from industry practitioners who employed the Leonard and Moselhi methodology, this study investigates the efficacy of a Recurrent Neural Network (RNN) architecture with Long Short-Term Memory (LSTM) cells. The model's performance is optimized through backpropagation and hyperparameter tuning, focusing on key parameters such as learning rate, batch size, dropout rate, and number of epochs. To ensure the model's generalizability and mitigate overfitting, regularization strategies and performance monitoring are employed. The predictive potential of the model is evaluated through integration into a real-time sequence production job and deployment into an enabled environment. Results demonstrate the model's capacity for accurate labour loss forecasting, enabling proactive measures to enhance productivity and minimize unnecessary claims. Although this study focuses on building projects, its findings have broader implications for process and manufacturing engineering, where productivity losses and associated labour losses are significant concerns. The practical application of this research lies in its potential to assess and counter labour loss claims, disputes, warrants, and demands in construction projects, ultimately contributing to improved project management and reduced financial losses.

Discover Civil EngineeringVol. 1(1)
Federal University of Technology Owerri (NG), Ambrose Alli University (NG)
Decent work and economic growth
Openalex Percentile: Top 40%
BIM and Construction Integration
0.27
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Exploring a recurrent neural network (RNN) earned value based model for predicting lost labour value in construction projects — Samuel I. Egwunatum, Joel Oboshior, et al. · Discover Civil Engineering (2024) | TGRS Research Map | TGRS