Determining Cost and Causes of Overruns in Infrastructure Projects in South Asia

Sustainable development is supported by infrastructure projects that have a long-term impact on economic development, societies, and the environment. In this paper, the aim is to estimate the cost performance, investigate the best-fit function for modeling the correlations between cost overruns and three variables, and identify the root causes of overruns in South Asian infrastructure projects. In the past, linear regression analysis has been utilized to model the correlations between cost overruns and project size, implementation period, and time overruns. Modeling these correlations requires the study and application of other regression functions. A database of 138 infrastructure projects from the South Asian region is established from the collected data. A methodology based on mixed methods for qualitative and quantitative data analysis is developed to achieve the aims of the paper. A mixed method encompasses a probabilistic and statistical approach alongside machine learning as quantitative methods and employs content analysis facilitated by NVivo v. 11 software as a qualitative method. Based on the results, the average cost overrun in infrastructure projects in South Asia is 3.3%. The random forest regression function, a machine learning technique, is tested as the most suitable function for modeling the impact between cost overruns and other variables compared to the linear and quadratic regression functions. The practical application is to support project stakeholders in the process of cost estimation during the decision-making phase of the project, to predict overruns in future infrastructure projects using machine learning techniques such as random forest regression, and to contribute to overall sustainable development.

Authors

Institutions

Publication Details

Journal
Sustainability
Published
2024-12-19
DOI
https://doi.org/10.3390/su162411159
Citations
5
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.45

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Determining Cost and Causes of Overruns in Infrastructure Projects in South Asia

Shuei‐Liong Lin, Bin Sun, Jelena M. Živković, Yuan Cheng
5 citations
Sustainability
Construction Project Management and Performance
2.45
article

Determining Cost and Causes of Overruns in Infrastructure Projects in South Asia

Shuei‐Liong Lin, Bin Sun, Jelena M. Živković, Yuan Cheng
article en
5 citations

Abstract

Sustainable development is supported by infrastructure projects that have a long-term impact on economic development, societies, and the environment. In this paper, the aim is to estimate the cost performance, investigate the best-fit function for modeling the correlations between cost overruns and three variables, and identify the root causes of overruns in South Asian infrastructure projects. In the past, linear regression analysis has been utilized to model the correlations between cost overruns and project size, implementation period, and time overruns. Modeling these correlations requires the study and application of other regression functions. A database of 138 infrastructure projects from the South Asian region is established from the collected data. A methodology based on mixed methods for qualitative and quantitative data analysis is developed to achieve the aims of the paper. A mixed method encompasses a probabilistic and statistical approach alongside machine learning as quantitative methods and employs content analysis facilitated by NVivo v. 11 software as a qualitative method. Based on the results, the average cost overrun in infrastructure projects in South Asia is 3.3%. The random forest regression function, a machine learning technique, is tested as the most suitable function for modeling the impact between cost overruns and other variables compared to the linear and quadratic regression functions. The practical application is to support project stakeholders in the process of cost estimation during the decision-making phase of the project, to predict overruns in future infrastructure projects using machine learning techniques such as random forest regression, and to contribute to overall sustainable development.

SustainabilityVol. 16(24)
Xi’an Jiaotong-Liverpool University (CN)
Xi’an Jiaotong-Liverpool University
Industry, innovation and infrastructure
Openalex Percentile: Top 10%
Construction Project Management and Performance
2.45
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.