Factor analysis of risk allocation criteria (RAC) in public-private partnership (PPP) projects: A case of New Zealand

The utilization of Public Private Partnerships (PPPs) has become widely prevalent as an innovative approach for procuring public infrastructure projects. Risk transfer/allocation is one of the main reasons for this widespread adoption and considered a critical success factor for a PPP. Given the importance of equitable risk allocation, this study identified and analysed 10 key risk allocation criteria. Experts with experience in PPP projects in New Zealand were surveyed through an empirical questionnaire to obtain industry-wide data. Mean score analysis and factor analysis were then used to analyse the collected data. In order to ensure the validity of the analysis results, appropriate statistical tests such as Cronbach’s Alpha, Kaiser-Meyer-Olkin (KMO) statistic and Bartlett’s test of Sphericity were conducted. Result indicate that the most important criteria for risk allocation are “risk foresight”, “minimize risk loss” and “response to risk”. Furthermore, factor analysis showed that the identified RAC can be classified into three component groups namely “risk management expertise”, “core risk management capability” and “risk management strategy”. This study aims to provide PPP stakeholders with useful insights into the most effective measures for achieving equitable risk allocation. To achieve this, the study recommends to consider the risk management capabilities of both the public and private sectors in light of the identified RACs/groupings. The results of the study are expected to assist PPP stakeholders in developing strategies that can enhance risk management and achieve a fair distribution of risks.

Authors

Institutions

Publication Details

Journal
Construction Economics and Building
Published
2024-09-26
DOI
https://doi.org/10.5130/ajceb.v24i4/5.9021
Citations
2
Primary Topic
Public-Private Partnership Projects
Type
article
Field-Weighted Citation Impact
1.11
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Factor analysis of risk allocation criteria (RAC) in public-private partnership (PPP) projects: A case of New Zealand

Nasir Rasheed, James Olabode Bamidele Rotimi, Wajiha Mohsin Shahzad
2 citations
Construction Economics and Building
Public-Private Partnership Projects
1.11
article

Factor analysis of risk allocation criteria (RAC) in public-private partnership (PPP) projects: A case of New Zealand

Nasir Rasheed, James Olabode Bamidele Rotimi, Wajiha Mohsin Shahzad
article en
2 citations

Abstract

The utilization of Public Private Partnerships (PPPs) has become widely prevalent as an innovative approach for procuring public infrastructure projects. Risk transfer/allocation is one of the main reasons for this widespread adoption and considered a critical success factor for a PPP. Given the importance of equitable risk allocation, this study identified and analysed 10 key risk allocation criteria. Experts with experience in PPP projects in New Zealand were surveyed through an empirical questionnaire to obtain industry-wide data. Mean score analysis and factor analysis were then used to analyse the collected data. In order to ensure the validity of the analysis results, appropriate statistical tests such as Cronbach’s Alpha, Kaiser-Meyer-Olkin (KMO) statistic and Bartlett’s test of Sphericity were conducted. Result indicate that the most important criteria for risk allocation are “risk foresight”, “minimize risk loss” and “response to risk”. Furthermore, factor analysis showed that the identified RAC can be classified into three component groups namely “risk management expertise”, “core risk management capability” and “risk management strategy”. This study aims to provide PPP stakeholders with useful insights into the most effective measures for achieving equitable risk allocation. To achieve this, the study recommends to consider the risk management capabilities of both the public and private sectors in light of the identified RACs/groupings. The results of the study are expected to assist PPP stakeholders in developing strategies that can enhance risk management and achieve a fair distribution of risks.

Construction Economics and BuildingVol. 24(4/5)
Massey University (NZ)
Partnerships for the goals
Openalex Percentile: Top 14%
Public-Private Partnership Projects
1.11
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Factor analysis of risk allocation criteria (RAC) in public-private partnership (PPP) projects: A case of New Zealand — Nasir Rasheed, James Olabode Bamidele Rotimi, et al. · Construction Economics and Building (2024) | TGRS Research Map | TGRS