BIM-Based Automatic Extraction of Daily Concrete and Formwork Requirements for Site Work Planning

Material planning is important in construction, for it affects procurement, cost, and schedule. Proper planning of material supply and logistics helps streamline the performance of all tasks through the avoidance of excessive or insufficient material supply. Material planning relies on quantity takeoff (QTO) and project schedules. Conventionally, quantity takeoff was a manual process based on 2D drawings and human interpretation and was error-prone. Presently, with the popularity of Building Information Modelling (BIM), in BIM-based projects, using inbuilt quantity takeoff functions, quantities of work can be generated automatically from BIM models to aid the quantity takeoff. However, if those inbuilt QTO solutions are object-based, then the quantities of works extracted may not meet the requirements of the users in selected cases, e.g., in zone-based construction projects. Also, for estimating daily material requirements, the accuracy of the quantities of work becomes more important, not only for the purpose of efficient planning but also for reducing construction waste. Since works using the same type of material can go overlapping, in addition to estimating the amount of material for each work, the total amount of material for a day must also be calculated. Thus, this research aims to develop a framework for automatic extraction of zone-based concrete volumes and formwork positions for cast-in-place concrete structures using the data in BIM models, followed by linking them with project schedules for estimating daily concrete and formwork requirements. This framework extends the body of knowledge by introducing an innovative algorithm for automatically calculating overlapped areas between concrete members and a rule for naming tasks in the schedule, followed by evaluating the formwork requirements without drawing formwork in a 3D model. A software tool will be developed to achieve the aim, and a case study will be used to validate the proposed framework.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2024-12-18
DOI
https://doi.org/10.3390/buildings14124021
Citations
4
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
1.06
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

BIM-Based Automatic Extraction of Daily Concrete and Formwork Requirements for Site Work Planning

Van-Hoan Pham, The-Quan Nguyen, Po‐Han Chen, D. Duong
4 citations
Buildings
BIM and Construction Integration
1.06
article

BIM-Based Automatic Extraction of Daily Concrete and Formwork Requirements for Site Work Planning

Van-Hoan Pham, The-Quan Nguyen, Po‐Han Chen, D. Duong
article en
4 citations

Abstract

Material planning is important in construction, for it affects procurement, cost, and schedule. Proper planning of material supply and logistics helps streamline the performance of all tasks through the avoidance of excessive or insufficient material supply. Material planning relies on quantity takeoff (QTO) and project schedules. Conventionally, quantity takeoff was a manual process based on 2D drawings and human interpretation and was error-prone. Presently, with the popularity of Building Information Modelling (BIM), in BIM-based projects, using inbuilt quantity takeoff functions, quantities of work can be generated automatically from BIM models to aid the quantity takeoff. However, if those inbuilt QTO solutions are object-based, then the quantities of works extracted may not meet the requirements of the users in selected cases, e.g., in zone-based construction projects. Also, for estimating daily material requirements, the accuracy of the quantities of work becomes more important, not only for the purpose of efficient planning but also for reducing construction waste. Since works using the same type of material can go overlapping, in addition to estimating the amount of material for each work, the total amount of material for a day must also be calculated. Thus, this research aims to develop a framework for automatic extraction of zone-based concrete volumes and formwork positions for cast-in-place concrete structures using the data in BIM models, followed by linking them with project schedules for estimating daily concrete and formwork requirements. This framework extends the body of knowledge by introducing an innovative algorithm for automatically calculating overlapped areas between concrete members and a rule for naming tasks in the schedule, followed by evaluating the formwork requirements without drawing formwork in a 3D model. A software tool will be developed to achieve the aim, and a case study will be used to validate the proposed framework.

BuildingsVol. 14(12)
National Taiwan University (TW), Hanoi University of Civil Engineering (VN), Concordia University (CA), Hanoi University (VN)
Openalex Percentile: Top 23%
BIM and Construction Integration
1.06
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.