Analysis of Material Supply Chain Risk Weight Using Severity Index Method

Material delay is a vital problem in the completion of construction work, this is closely related to the understanding of the flow of material supply. So it takes risk weight analysis from the internal side (supply, control, process, demand) and external (disaster factor). This study began with a literature study to obtain a list of risks, then data collection using a questionnaire method to 50 respondents who are experts in construction material procurement. Furthermore, a risk analysis was carried out using the severity index method. From this analysis, the average risk from the supply side was 16.40%, the control risk was 16.29%, the process risk was 11%, the demand risk was 16.11% and the disaster risk was 13.79%. There are two most dominant delay risks, namely material delays due to constraints in the factory process to material limitations at the supplier and late payments from the main contractor to the subcontractor so that material orders are late.

Authors

Institutions

Publication Details

Journal
Jurnal Inotera
Published
2024-12-16
DOI
https://doi.org/10.31572/inotera.vol9.iss2.2024.id423
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Material Supply Chain Risk Weight Using Severity Index Method

Lisherly Debataraja, Marsedes Purba, Amrizal, Gallio Budianto et al.
Jurnal Inotera
Management and Optimization Techniques
article

Analysis of Material Supply Chain Risk Weight Using Severity Index Method

Lisherly Debataraja, Marsedes Purba, Amrizal, Gallio Budianto, Naga Raya Sinaga
article en

Abstract

Material delay is a vital problem in the completion of construction work, this is closely related to the understanding of the flow of material supply. So it takes risk weight analysis from the internal side (supply, control, process, demand) and external (disaster factor). This study began with a literature study to obtain a list of risks, then data collection using a questionnaire method to 50 respondents who are experts in construction material procurement. Furthermore, a risk analysis was carried out using the severity index method. From this analysis, the average risk from the supply side was 16.40%, the control risk was 16.29%, the process risk was 11%, the demand risk was 16.11% and the disaster risk was 13.79%. There are two most dominant delay risks, namely material delays due to constraints in the factory process to material limitations at the supplier and late payments from the main contractor to the subcontractor so that material orders are late.

Jurnal InoteraVol. 9(2)
State University of Medan (ID)
Climate action
Openalex Percentile: Top 60%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.