Analisis Akar Masalah Keterlambatan Pengerjaan pada Proyek Konstruksi Politeknik Maritim Negeri Indonesia

The construction industry in Indonesia is growing rapidly, playing a crucial role in the country's economic, political, and social development. However, alongside this rapid growth, issues such as project delays are inevitable. The construction project of the Indonesian Maritime Polytechnic, for instance, has experienced significant delays, which can lead to increased costs, waste of human resources, and disputes among the involved parties. Understanding the primary causes of these delays is essential for developing effective strategies to avoid future delays. This analysis uses both qualitative and quantitative methods to identify the root causes of delays. Data was collected through surveys of respondents involved in the project, including project managers, field staff, and consultants. The analyzed causes of delays include insufficient funding, increases in raw material costs, additional costs, contract document errors, poor communication, and slow decision-making. To minimize delays and their impacts, several recommendations can be made: effective strategic planning, improved communication, increased staff, accurate initial cost estimates, and good management. By implementing these recommendations, the Indonesian Maritime Polytechnic construction project can be completed more effectively and efficiently, and future delays can be avoided.

Authors

Institutions

Publication Details

Journal
Venus Jurnal Publikasi Rumpun Ilmu Teknik 
Published
2024-12-12
DOI
https://doi.org/10.61132/venus.v2i6.647
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analisis Akar Masalah Keterlambatan Pengerjaan pada Proyek Konstruksi Politeknik Maritim Negeri Indonesia

Koosdaryani Soeryodarundio, Ary Setyawan, Naufal Iman Adzhan
Venus Jurnal Publikasi Rumpun Ilmu Teknik 
Occupational Health and Safety Management
article

Analisis Akar Masalah Keterlambatan Pengerjaan pada Proyek Konstruksi Politeknik Maritim Negeri Indonesia

Koosdaryani Soeryodarundio, Ary Setyawan, Naufal Iman Adzhan
article en

Abstract

The construction industry in Indonesia is growing rapidly, playing a crucial role in the country's economic, political, and social development. However, alongside this rapid growth, issues such as project delays are inevitable. The construction project of the Indonesian Maritime Polytechnic, for instance, has experienced significant delays, which can lead to increased costs, waste of human resources, and disputes among the involved parties. Understanding the primary causes of these delays is essential for developing effective strategies to avoid future delays. This analysis uses both qualitative and quantitative methods to identify the root causes of delays. Data was collected through surveys of respondents involved in the project, including project managers, field staff, and consultants. The analyzed causes of delays include insufficient funding, increases in raw material costs, additional costs, contract document errors, poor communication, and slow decision-making. To minimize delays and their impacts, several recommendations can be made: effective strategic planning, improved communication, increased staff, accurate initial cost estimates, and good management. By implementing these recommendations, the Indonesian Maritime Polytechnic construction project can be completed more effectively and efficiently, and future delays can be avoided.

Venus Jurnal Publikasi Rumpun Ilmu Teknik Vol. 2(6)
Sebelas Maret University (ID)
Openalex Percentile: Top 59%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.