Developing a community responsive resilient contractor selection model for post-disaster reconstruction projects: a build back better approach

Purpose This study aims to develop a resilient contractor selection model that also considers community concerns in post-disaster reconstruction projects using a “build-back better (BBB)” approach. Design/methodology/approach At the outset, a comprehensive literature review was conducted to develop the model. During this literature review, a set of contractor selection criteria were identified. Focus group discussion (FGD) sessions were then organized to revise and refine the identified criteria. As a result, a final list of 39 selection criteria was developed. Next, the Bayesian best worst method (BBWM) was conducted to determine the weights of each selection criterion. Finally, the proposed model was validated by conducting a hypothetical case study and fuzzy VlseKriterijuska Optimizacija I Komoromisno Resenje (fuzzy VIKOR) analysis. Moreover, a sensitivity analysis was conducted to examine the effect of the maximum group utility (v) value in the model. Findings The results emphasized that contractors in post-disaster reconstruction projects cannot be selected merely based on “technical” and “economic” factors. Instead, the other aspects, namely “organizational and managerial,” “environmental sustainability,” “resource management and procurement” and “end-user,” should also be taken into consideration. Second, factors related to financial strength, experience, risk management, energy efficiency, resource availability and assurance were particularly deemed the most significant, needing the detailed attention of the decision-makers. Lastly, the case study revealed that the proposed model has a significant potential to systemize contractor selection processes in post-disaster reconstruction projects. Originality/value Disasters, which are increasing in frequency and severity today, devastate the community’s environmental, economic and social conditions. Post-disaster reconstruction projects commence rapidly after a disaster for recovery. However, poor management procedures in these projects trigger time and cost overruns. Unlike traditional construction projects, post-disaster reconstruction projects are distinctive due to the uncertainties caused by the disasters and the prioritization of community concerns. Therefore, contractors should be selected in a way that can meet the specific needs of reconstruction projects. Otherwise, resilience in the built environment and community satisfaction can hardly be enhanced. Accordingly, this study is one of the first attempts to develop a contractor selection model for post-disaster reconstruction projects. It is believed that the developed model will make essential theoretical and practical contributions to the post-disaster reconstruction domain.

Authors

Institutions

Publication Details

Journal
Engineering Construction & Architectural Management
Published
2024-12-12
DOI
https://doi.org/10.1108/ecam-06-2024-0802
Citations
5
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.45
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Developing a community responsive resilient contractor selection model for post-disaster reconstruction projects: a build back better approach

Zeynep Işık, Fehmi Samet Demirci
5 citations
Engineering Construction & Architectural Management
Construction Project Management and Performance
2.45
article

Developing a community responsive resilient contractor selection model for post-disaster reconstruction projects: a build back better approach

Zeynep Işık, Fehmi Samet Demirci
article en
5 citations

Abstract

Purpose This study aims to develop a resilient contractor selection model that also considers community concerns in post-disaster reconstruction projects using a “build-back better (BBB)” approach. Design/methodology/approach At the outset, a comprehensive literature review was conducted to develop the model. During this literature review, a set of contractor selection criteria were identified. Focus group discussion (FGD) sessions were then organized to revise and refine the identified criteria. As a result, a final list of 39 selection criteria was developed. Next, the Bayesian best worst method (BBWM) was conducted to determine the weights of each selection criterion. Finally, the proposed model was validated by conducting a hypothetical case study and fuzzy VlseKriterijuska Optimizacija I Komoromisno Resenje (fuzzy VIKOR) analysis. Moreover, a sensitivity analysis was conducted to examine the effect of the maximum group utility (v) value in the model. Findings The results emphasized that contractors in post-disaster reconstruction projects cannot be selected merely based on “technical” and “economic” factors. Instead, the other aspects, namely “organizational and managerial,” “environmental sustainability,” “resource management and procurement” and “end-user,” should also be taken into consideration. Second, factors related to financial strength, experience, risk management, energy efficiency, resource availability and assurance were particularly deemed the most significant, needing the detailed attention of the decision-makers. Lastly, the case study revealed that the proposed model has a significant potential to systemize contractor selection processes in post-disaster reconstruction projects. Originality/value Disasters, which are increasing in frequency and severity today, devastate the community’s environmental, economic and social conditions. Post-disaster reconstruction projects commence rapidly after a disaster for recovery. However, poor management procedures in these projects trigger time and cost overruns. Unlike traditional construction projects, post-disaster reconstruction projects are distinctive due to the uncertainties caused by the disasters and the prioritization of community concerns. Therefore, contractors should be selected in a way that can meet the specific needs of reconstruction projects. Otherwise, resilience in the built environment and community satisfaction can hardly be enhanced. Accordingly, this study is one of the first attempts to develop a contractor selection model for post-disaster reconstruction projects. It is believed that the developed model will make essential theoretical and practical contributions to the post-disaster reconstruction domain.

Engineering Construction & Architectural ManagementVol. 33(2)
Yıldız Technical University (TR)
Openalex Percentile: Top 10%
Construction Project Management and Performance
2.45
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.