Sustainable Solutions for Metro Project Delays: Lean Practices for Enhanced Resource Efficiency and Cleaner Production

Construction projects in metro areas often experience big delays, which make the projects take longer, cost more, and use resources less efficiently. Getting rid of these delays is necessary to make the project run more smoothly and waste less material, which is in line with the ideals of smarter production. This study’s goal is to find, examine, and rank the most important reasons that cause Indian metro projects to be late while also suggesting long-term answers that use lean methods. This study is needed because train projects are becoming more complicated, and people want more environmentally friendly building methods. A total of 38 people from the government, business, and other building sectors filled out an organized questionnaire poll that was used to collect data. To get a full picture of the delay factors, a quantitative approach was used. This included a Likert scale, ranking, percentage analysis, the relative importance index (RII), and SPSS analysis. These methods were picked to make sure that the delays were accurately measured and that answers could be put in order of importance. This study found 19 specific reasons for delay and put them into seven main groups. The results show that delays are mostly caused by links to utilities and other equipment outside the building. Lean methods, which focus on reducing waste and making the best use of resources, are suggested as good ways to cut down on these delays and encourage better production in metro building projects.

Authors

Institutions

Publication Details

Journal
Sustainability
Published
2024-12-12
DOI
https://doi.org/10.3390/su162410897
Citations
5
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
2.45
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Sustainable Solutions for Metro Project Delays: Lean Practices for Enhanced Resource Efficiency and Cleaner Production

T. Senthil Vadivel, Vaishali Sahu, Lilesh Gautam, Ardra Suseelan et al.
5 citations
Sustainability
Construction Project Management and Performance
2.45
article

Sustainable Solutions for Metro Project Delays: Lean Practices for Enhanced Resource Efficiency and Cleaner Production

T. Senthil Vadivel, Vaishali Sahu, Lilesh Gautam, Ardra Suseelan, Robin Singh
article en
5 citations

Abstract

Construction projects in metro areas often experience big delays, which make the projects take longer, cost more, and use resources less efficiently. Getting rid of these delays is necessary to make the project run more smoothly and waste less material, which is in line with the ideals of smarter production. This study’s goal is to find, examine, and rank the most important reasons that cause Indian metro projects to be late while also suggesting long-term answers that use lean methods. This study is needed because train projects are becoming more complicated, and people want more environmentally friendly building methods. A total of 38 people from the government, business, and other building sectors filled out an organized questionnaire poll that was used to collect data. To get a full picture of the delay factors, a quantitative approach was used. This included a Likert scale, ranking, percentage analysis, the relative importance index (RII), and SPSS analysis. These methods were picked to make sure that the delays were accurately measured and that answers could be put in order of importance. This study found 19 specific reasons for delay and put them into seven main groups. The results show that delays are mostly caused by links to utilities and other equipment outside the building. Lean methods, which focus on reducing waste and making the best use of resources, are suggested as good ways to cut down on these delays and encourage better production in metro building projects.

SustainabilityVol. 16(24)
The NorthCap University (IN), Manav Rachna International Institute of Research and Studies (IN)
Decent work and economic growth
Openalex Percentile: Top 10%
Construction Project Management and Performance
2.45
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.