Swiss highway project cost estimate performance: Deviations from norms and expected trends

• Swiss highway construction project median cost overrun is 4.7%. • Projects overrun costs during planning phases, and underrun during construction. • Each additional year of planning increases cost overrun by 4%. • Cost estimating norms do not reflect observed cost deviations. Cost overruns in construction projects are a common issue internationally, and project cost performance in individual countries varies considerably. Countries that lack systematic project data may rely on foreign data for informing cost estimating practices and norms, which may lead to errors. This study considered the case of Switzerland, a country with limited research on construction project cost performance. Swiss highway construction projects were analysed to assess the accuracy of cost estimating methods and norms. Different factors influencing cost overruns were considered: project size, type, planning duration, start year, and historical policy changes. The results revealed that the general patterns of cost overruns observed internationally do not apply to Switzerland: projects tend to overrun estimated costs during the planning phase but underrun during the construction phase, leading to accurate overall cost estimates (4.7% median overrun). Projects exhibited large and asymmetrical cost accuracy ranges throughout the planning and construction phases. These results deviate from expectations set in norms and comparable international project data. Based on these findings, the study challenges the effectiveness of current Swiss cost estimating norms, suggesting a need for more country-specific data analysis and policy development.

Authors

Institutions

Publication Details

Journal
Case Studies on Transport Policy
Published
2024-12-10
DOI
https://doi.org/10.1016/j.cstp.2024.101344
Citations
2
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.98
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Swiss highway project cost estimate performance: Deviations from norms and expected trends

Bryan T. Adey, David Zani
2 citations
Case Studies on Transport Policy
Construction Project Management and Performance
0.98
article

Swiss highway project cost estimate performance: Deviations from norms and expected trends

Bryan T. Adey, David Zani
article en
2 citations

Abstract

• Swiss highway construction project median cost overrun is 4.7%. • Projects overrun costs during planning phases, and underrun during construction. • Each additional year of planning increases cost overrun by 4%. • Cost estimating norms do not reflect observed cost deviations. Cost overruns in construction projects are a common issue internationally, and project cost performance in individual countries varies considerably. Countries that lack systematic project data may rely on foreign data for informing cost estimating practices and norms, which may lead to errors. This study considered the case of Switzerland, a country with limited research on construction project cost performance. Swiss highway construction projects were analysed to assess the accuracy of cost estimating methods and norms. Different factors influencing cost overruns were considered: project size, type, planning duration, start year, and historical policy changes. The results revealed that the general patterns of cost overruns observed internationally do not apply to Switzerland: projects tend to overrun estimated costs during the planning phase but underrun during the construction phase, leading to accurate overall cost estimates (4.7% median overrun). Projects exhibited large and asymmetrical cost accuracy ranges throughout the planning and construction phases. These results deviate from expectations set in norms and comparable international project data. Based on these findings, the study challenges the effectiveness of current Swiss cost estimating norms, suggesting a need for more country-specific data analysis and policy development.

Case Studies on Transport PolicyVol. 19
ETH Zurich (CH)
Sustainable cities and communities
Openalex Percentile: Top 20%
Construction Project Management and Performance
0.98
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Swiss highway project cost estimate performance: Deviations from norms and expected trends — Bryan T. Adey, David Zani · Case Studies on Transport Policy (2024) | TGRS Research Map | TGRS