Grid connection barriers to renewable energy deployment in the United States

<h2>Summary</h2> Bulk-power grid connection is an emerging bottleneck to the entry of wind, solar, and storage but has been understudied due to a lack of data. We create and analyze two novel interconnection datasets with more than 38,000 project-level observations that provide new information documenting interconnection challenges in the United States. Active grid connection requests are more than double the total installed capacity of the US power plant fleet (2,600 vs. 1,280 GW). The time required to secure a connection has increased by 70% over the last decade, and withdrawal rates remain high at 80%, suggesting a constrained transmission system that jeopardizes energy transition targets. Wide distributions of interconnection costs indicate the inherent uncertainty of the interconnection process. Interconnection requests that identify large transmission upgrades tend to withdraw from the process. These findings suggest the need for interconnection reforms, tighter links between long-term transmission planning and project-level interconnection processes, and more interconnection outcome transparency.

Authors

Institutions

Publication Details

Journal
Joule
Published
2024-12-06
DOI
https://doi.org/10.1016/j.joule.2024.11.008
Citations
37
Primary Topic
Social Acceptance of Renewable Energy
Type
article
Field-Weighted Citation Impact
41.88

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Grid connection barriers to renewable energy deployment in the United States

Julie Mulvaney-Kemp, Fredrich Kahrl, Joseph Rand, Ryan Wiser et al.
37 citations
Joule
Social Acceptance of Renewable Energy
41.88
article

Grid connection barriers to renewable energy deployment in the United States

Julie Mulvaney-Kemp, Fredrich Kahrl, Joseph Rand, Ryan Wiser, Joachim Seel, Will Cotton, Nick Manderlink, Kevin R. Porter, Will Gorman
article en
37 citations

Abstract

<h2>Summary</h2> Bulk-power grid connection is an emerging bottleneck to the entry of wind, solar, and storage but has been understudied due to a lack of data. We create and analyze two novel interconnection datasets with more than 38,000 project-level observations that provide new information documenting interconnection challenges in the United States. Active grid connection requests are more than double the total installed capacity of the US power plant fleet (2,600 vs. 1,280 GW). The time required to secure a connection has increased by 70% over the last decade, and withdrawal rates remain high at 80%, suggesting a constrained transmission system that jeopardizes energy transition targets. Wide distributions of interconnection costs indicate the inherent uncertainty of the interconnection process. Interconnection requests that identify large transmission upgrades tend to withdraw from the process. These findings suggest the need for interconnection reforms, tighter links between long-term transmission planning and project-level interconnection processes, and more interconnection outcome transparency.

JouleVol. 9(2)
Lawrence Berkeley National Laboratory (US), Phillips Exeter Academy (US), Cardiovascular Research Associates (US), AIL Research (United States) (US)
U.S. Department of Energy, Office of Energy Efficiency and Renewable Energy, Wind Energy Technologies Office, Solar Energy Technologies Office
Affordable and clean energy
Openalex Percentile: Top 0%
Social Acceptance of Renewable Energy
41.88
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.