A delay-time-based postponed replacement-spare part provision policy with adaptive inspection

Collaborative management of maintenance and spare part provision plays a significant role in promoting the operation efficiency and reducing failure risks for industrial assets. This paper devises a postponed replacement-spare part provision policy based on delay time model under two-phase adaptive inspection. The first-phase inspection with longer interval is enforced only once, and is substituted via second-phase inspection with shorter interval subsequently. Following the inspection outcomes, the system is preventive renewed when the postponed ordered part, triggered with a delayed interval after the defect identification, is available; otherwise it is corrective restored via ordinary or urgent order, depending upon the various failure times compared with the order induced by defect identification. The proposed policy not only mitigates the unnecessary economy losses when it operates initially, but utilizes the remaining useful lifetime to a great extent. The applicability is demonstrated via a numerical experiment.

Authors

Institutions

Publication Details

Published
2024-10-11
DOI
https://doi.org/10.1109/srse63568.2024.10772539
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A delay-time-based postponed replacement-spare part provision policy with adaptive inspection

Xiaobing Ma, Heping Jia, Jiantai Wang, Li Yang
Management and Optimization Techniques
article

A delay-time-based postponed replacement-spare part provision policy with adaptive inspection

Xiaobing Ma, Heping Jia, Jiantai Wang, Li Yang
article en

Abstract

Collaborative management of maintenance and spare part provision plays a significant role in promoting the operation efficiency and reducing failure risks for industrial assets. This paper devises a postponed replacement-spare part provision policy based on delay time model under two-phase adaptive inspection. The first-phase inspection with longer interval is enforced only once, and is substituted via second-phase inspection with shorter interval subsequently. Following the inspection outcomes, the system is preventive renewed when the postponed ordered part, triggered with a delayed interval after the defect identification, is available; otherwise it is corrective restored via ordinary or urgent order, depending upon the various failure times compared with the order induced by defect identification. The proposed policy not only mitigates the unnecessary economy losses when it operates initially, but utilizes the remaining useful lifetime to a great extent. The applicability is demonstrated via a numerical experiment.

North China Electric Power University (CN), Beihang University (CN)
National Natural Science Foundation of China
Climate action
Openalex Percentile: Top 62%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.