Time and cost performance analysis: earned value management method on HPK Project Using Mobox

Conventional construction methods have proven inadequate for meeting the accelerated development needs of IKN, highlighting the necessity for innovative approaches to expedite construction. Additionally, challenges related to material supply further exacerbate the situation. The Mobox method emerges as a promising alternative, offering potential to streamline project completion. This study compares time performance between conventional concrete methods, which typically require 7 months, and the Mobox method, which achieves the same in 4 months. The aim is to evaluate whether time and cost performance align with the project owner's expectations, using the Earned Value Management (EVM) method for a 4-storey building project utilizing Mobox modular construction. At week 16, the project’s time performance met expectations, as evidenced by a Schedule Variance (SV) of zero and a Schedule Performance Index (SPI) of 1. Cost performance also exceeded expectations, with a positive Cost Variance (CV) of Rp 11,784,790,045.29 and a Cost Performance Index (CPI) of 1.023, indicating cost efficiency. The Mobox method, coupled with the EVM approach, proves to be an effective and efficient alternative for construction projects, demonstrating the capability to complete projects on time and within budget while maintaining quality.

Authors

Institutions

Publication Details

Journal
Teknisia
Published
2024-09-30
DOI
https://doi.org/10.20885/teknisia.vol29.iss1.art6
Primary Topic
Value Engineering and Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Time and cost performance analysis: earned value management method on HPK Project Using Mobox

Budi Susetyo, Vegit Risana Hughes
Teknisia
Value Engineering and Management
article

Time and cost performance analysis: earned value management method on HPK Project Using Mobox

Budi Susetyo, Vegit Risana Hughes
article en

Abstract

Conventional construction methods have proven inadequate for meeting the accelerated development needs of IKN, highlighting the necessity for innovative approaches to expedite construction. Additionally, challenges related to material supply further exacerbate the situation. The Mobox method emerges as a promising alternative, offering potential to streamline project completion. This study compares time performance between conventional concrete methods, which typically require 7 months, and the Mobox method, which achieves the same in 4 months. The aim is to evaluate whether time and cost performance align with the project owner's expectations, using the Earned Value Management (EVM) method for a 4-storey building project utilizing Mobox modular construction. At week 16, the project’s time performance met expectations, as evidenced by a Schedule Variance (SV) of zero and a Schedule Performance Index (SPI) of 1. Cost performance also exceeded expectations, with a positive Cost Variance (CV) of Rp 11,784,790,045.29 and a Cost Performance Index (CPI) of 1.023, indicating cost efficiency. The Mobox method, coupled with the EVM approach, proves to be an effective and efficient alternative for construction projects, demonstrating the capability to complete projects on time and within budget while maintaining quality.

TeknisiaVol. 29(1)
Mercu Buana University (ID)
Openalex Percentile: Top 62%
Value Engineering and Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.