Economic Feasibility of On-Grid Photovoltaic Solar Power Plants at Private Universities in Indonesia

Campus 2 of the National Institute of Technology (ITN) Malang shows its commitment to utilizing solar energy by adopting a 500 kWp photovoltaic solar power plant (PV), making it the largest in Indonesia for a private university. This research aims to evaluate the economic feasibility of photovoltaic solar power plants (PV) at Campus 2 of the National Institute of Technology Malang. The implementation of renewable energy, particularly photovoltaic solar power, is gaining attention due to its contribution to reducing greenhouse gas emissions and economic growth. However, the development of renewable energy sources faces several challenges, including the limitations of economic feasibility studies in Indonesia. A mixed-methods research approach is used, combining qualitative and quantitative data. Qualitative data are obtained from interviews with PV management staff, while quantitative data include net present value (NPV) calculations and payback periods (PBP). The research findings indicate that the on-grid photovoltaic solar power plant at Campus 2 of the National Institute of Technology (ITN) Malang has a capacity of 500 kWp, with a peak load reaching 380 kVA. The total project cost is Rp. 4,084,498,826, with annual operational and maintenance costs of Rp. 81,595,607. The price of electricity from the on-grid photovoltaic solar power plant is Rp. 930 per kWh. An NPV value of Rp. 7,789,395,602 indicates future profitability, while a PBP of 8.55 years demonstrates feasibility in terms of return on investment. In conclusion, the on-grid photovoltaic solar power plant at Campus 2 of the National Institute of Technology Malang has good economic feasibility due to factors such as controlled costs, competitive prices, a positive NPV, and a short PBP. Regular evaluations are necessary to ensure efficient operation and maximum benefits.

Authors

Publication Details

Journal
Nature Environment and Pollution Technology
Published
2024-12-01
DOI
https://doi.org/10.46488/nept.2024.v23i04.011
Citations
3
Primary Topic
Hybrid Renewable Energy Systems
Type
article
Field-Weighted Citation Impact
0.51
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Economic Feasibility of On-Grid Photovoltaic Solar Power Plants at Private Universities in Indonesia

Rijal Asnawi, Aminudin Afandhi, Antariksa Antariksa, Sukir Maryanto
3 citations
Nature Environment and Pollution Technology
Hybrid Renewable Energy Systems
0.51
article

Economic Feasibility of On-Grid Photovoltaic Solar Power Plants at Private Universities in Indonesia

Rijal Asnawi, Aminudin Afandhi, Antariksa Antariksa, Sukir Maryanto
article en
3 citations

Abstract

Campus 2 of the National Institute of Technology (ITN) Malang shows its commitment to utilizing solar energy by adopting a 500 kWp photovoltaic solar power plant (PV), making it the largest in Indonesia for a private university. This research aims to evaluate the economic feasibility of photovoltaic solar power plants (PV) at Campus 2 of the National Institute of Technology Malang. The implementation of renewable energy, particularly photovoltaic solar power, is gaining attention due to its contribution to reducing greenhouse gas emissions and economic growth. However, the development of renewable energy sources faces several challenges, including the limitations of economic feasibility studies in Indonesia. A mixed-methods research approach is used, combining qualitative and quantitative data. Qualitative data are obtained from interviews with PV management staff, while quantitative data include net present value (NPV) calculations and payback periods (PBP). The research findings indicate that the on-grid photovoltaic solar power plant at Campus 2 of the National Institute of Technology (ITN) Malang has a capacity of 500 kWp, with a peak load reaching 380 kVA. The total project cost is Rp. 4,084,498,826, with annual operational and maintenance costs of Rp. 81,595,607. The price of electricity from the on-grid photovoltaic solar power plant is Rp. 930 per kWh. An NPV value of Rp. 7,789,395,602 indicates future profitability, while a PBP of 8.55 years demonstrates feasibility in terms of return on investment. In conclusion, the on-grid photovoltaic solar power plant at Campus 2 of the National Institute of Technology Malang has good economic feasibility due to factors such as controlled costs, competitive prices, a positive NPV, and a short PBP. Regular evaluations are necessary to ensure efficient operation and maximum benefits.

Nature Environment and Pollution TechnologyVol. 23(4)
Affordable and clean energy
Openalex Percentile: Top 29%
Hybrid Renewable Energy Systems
0.51
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Economic Feasibility of On-Grid Photovoltaic Solar Power Plants at Private Universities in Indonesia — Rijal Asnawi, Aminudin Afandhi, et al. · Nature Environment and Pollution Technology (2024) | TGRS Research Map | TGRS