Streamlining Meatball Manufacturing: Lean Principles and Efficiency Improvements

Initial observations of a meatball manufacturing company revealed inefficiencies, including defective meatballs and work-in-process accumulation. Research aimed to identify and analyze these inefficiencies, design a future state map by using value stream map, and test improvements using Flexsim simulation software. Focusing on type X meatballs, which constitute 39.63% of sales, calculations showed a total cycle time of 4951.27 seconds and a lead time of 5507.50 seconds, with a takt time of 960 seconds per batch. The drying process was identified as the bottleneck, with the current process cycle efficiency (PCE) at 88.46%, surpassing the 30% threshold for a lean process. Waste was noted in defects, inventory, and motion. The proposed improvement added one operator to the packing workstation, increasing the number to four. This adjustment reduced the average waiting time on the packing rack by 87.62 % and increased the total output of finished goods by 19.15%.

Authors

Institutions

Publication Details

Published
2024-09-12
DOI
https://doi.org/10.1109/ictiia61827.2024.10761556
Primary Topic
Quality and Supply Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Streamlining Meatball Manufacturing: Lean Principles and Efficiency Improvements

Laurence Laurence, Anthony Matthew
Quality and Supply Management
article

Streamlining Meatball Manufacturing: Lean Principles and Efficiency Improvements

Laurence Laurence, Anthony Matthew
article en

Abstract

Initial observations of a meatball manufacturing company revealed inefficiencies, including defective meatballs and work-in-process accumulation. Research aimed to identify and analyze these inefficiencies, design a future state map by using value stream map, and test improvements using Flexsim simulation software. Focusing on type X meatballs, which constitute 39.63% of sales, calculations showed a total cycle time of 4951.27 seconds and a lead time of 5507.50 seconds, with a takt time of 960 seconds per batch. The drying process was identified as the bottleneck, with the current process cycle efficiency (PCE) at 88.46%, surpassing the 30% threshold for a lean process. Waste was noted in defects, inventory, and motion. The proposed improvement added one operator to the packing workstation, increasing the number to four. This adjustment reduced the average waiting time on the packing rack by 87.62 % and increased the total output of finished goods by 19.15%.

Pelita Harapan University (ID)
Openalex Percentile: Top 66%
Quality and Supply Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.