ANALISIS KINERJA PROYEK PEMBANGUNAN RUMAH SAKIT PANTI BHAKTININGSIH CHARITAS KECAMATAN BELITANG, KABUPATEN OKU TIMUR

In a project, planning and controlling time and cost is parts of contruction management project completely, Earned Value concept is one of method that can monitoring project’s performance from the cost and time goodly. This research has aim to know project’s performance from the time and cost side weekly, predict cost and time for job finishing rest of jobs. So it can get correction action what next will do for project developing. It use Earned Value Analisys by collecting data in the field development project Panti Bhaktiningsih Charitas Belitang Hospital. The results of the analysis of the Panti Bhaktiningsih Charitas Belitang Hospital construction project, namely the actual cost to complete the Panti Bhaktiningsih Charitas Belitang Hospital construction project from May 2017 to July 2018 was Rp. 19,883,148,800 with a Schedule Performance Index (SPI) value of 0.887 while the Cost Performance Index (CPI) was 1.034, which means that the project experienced delays in terms of schedule but incurred actual costs that were less than the work that had been carried out. Estimate to Completion (ETC) value is Rp. 7.333.436.666 and Estimate Cost at Completion (EAC) value is Rp.27.216.585.466,00 whereas Estimated Completion Date (ECD) value become 558 days from finishing the project.

Authors

Institutions

Publication Details

Journal
Jurnal Teknik Sipil LATERAL
Published
2024-11-20
DOI
https://doi.org/10.52333/lateral.v2i2.767
Primary Topic
Occupational Health and Safety Management
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ANALISIS KINERJA PROYEK PEMBANGUNAN RUMAH SAKIT PANTI BHAKTININGSIH CHARITAS KECAMATAN BELITANG, KABUPATEN OKU TIMUR

Fajar Sadik Islami, Ani Firda, Indra Syahrul Fuad, Poppy Augustina Legislatifa et al.
Jurnal Teknik Sipil LATERAL
Occupational Health and Safety Management
article

ANALISIS KINERJA PROYEK PEMBANGUNAN RUMAH SAKIT PANTI BHAKTININGSIH CHARITAS KECAMATAN BELITANG, KABUPATEN OKU TIMUR

Fajar Sadik Islami, Ani Firda, Indra Syahrul Fuad, Poppy Augustina Legislatifa, Adefan Hendric
article en

Abstract

In a project, planning and controlling time and cost is parts of contruction management project completely, Earned Value concept is one of method that can monitoring project’s performance from the cost and time goodly. This research has aim to know project’s performance from the time and cost side weekly, predict cost and time for job finishing rest of jobs. So it can get correction action what next will do for project developing. It use Earned Value Analisys by collecting data in the field development project Panti Bhaktiningsih Charitas Belitang Hospital. The results of the analysis of the Panti Bhaktiningsih Charitas Belitang Hospital construction project, namely the actual cost to complete the Panti Bhaktiningsih Charitas Belitang Hospital construction project from May 2017 to July 2018 was Rp. 19,883,148,800 with a Schedule Performance Index (SPI) value of 0.887 while the Cost Performance Index (CPI) was 1.034, which means that the project experienced delays in terms of schedule but incurred actual costs that were less than the work that had been carried out. Estimate to Completion (ETC) value is Rp. 7.333.436.666 and Estimate Cost at Completion (EAC) value is Rp.27.216.585.466,00 whereas Estimated Completion Date (ECD) value become 558 days from finishing the project.

Jurnal Teknik Sipil LATERALVol. 2(2)
Sriwijaya University (ID), Universitas Tridinanti Palembang (ID)
Industry, innovation and infrastructure
Openalex Percentile: Top 62%
Occupational Health and Safety Management
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ANALISIS KINERJA PROYEK PEMBANGUNAN RUMAH SAKIT PANTI BHAKTININGSIH CHARITAS KECAMATAN BELITANG, KABUPATEN OKU TIMUR — Fajar Sadik Islami, Ani Firda, et al. · Jurnal Teknik Sipil LATERAL (2024) | TGRS Research Map | TGRS