Fuzzy repetitive scheduling for construction projects considering risk preferences and time-cost tradeoffs

Purpose The purpose of this study is to develop a novel approach that addresses time-cost tradeoffs in repetitive construction projects while considering the uncertainty in activity durations and the risk preferences of planners. Design/methodology/approach Our study involves work in three aspects. Firstly, it employs triangular fuzzy numbers to represent activity durations in different units, which facilitates the management of scenarios characterized by limited historical data or the presence of ambiguous information. Secondly, it introduces a fuzzy chance-constrained programming model, which is aimed at minimizing the project budget while ensuring that the risks associated with cost overruns and schedule delays are confined to specified limits. Thirdly, it advances an enhanced genetic algorithm, integrating an electromagnetism-like mechanism and a scheduling repair process, to improve the efficiency and effectiveness of the optimization process. Findings A real-life street renovation project was analyzed to demonstrate the applicability of the proposed algorithm. The analysis explored three common types of risk preferences: risk-averse, risk-neutral and risk-loving. The results indicate that the proposed algorithm surpasses existing fuzzy repetitive scheduling methods in terms of risk management. It effectively generates schedules that align with the risk preferences of planners and provides worst-case estimates of project performance. Originality/value This research makes a significant contribution to the field by developing a fuzzy chance-constrained programming model and an associated optimization algorithm that is specifically designed for time-cost tradeoffs in repetitive construction projects. A key distinction is that this study considers the risk preferences of planners, which sets it apart from previously developed models. As a result, it provides a practical approach for effective risk management.

Authors

Institutions

Publication Details

Journal
Engineering Construction & Architectural Management
Published
2024-11-29
DOI
https://doi.org/10.1108/ecam-09-2023-0910
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Fuzzy repetitive scheduling for construction projects considering risk preferences and time-cost tradeoffs

Xin Zou, Lihui Zhang
Engineering Construction & Architectural Management
Resource-Constrained Project Scheduling
article

Fuzzy repetitive scheduling for construction projects considering risk preferences and time-cost tradeoffs

Xin Zou, Lihui Zhang
article en

Abstract

Purpose The purpose of this study is to develop a novel approach that addresses time-cost tradeoffs in repetitive construction projects while considering the uncertainty in activity durations and the risk preferences of planners. Design/methodology/approach Our study involves work in three aspects. Firstly, it employs triangular fuzzy numbers to represent activity durations in different units, which facilitates the management of scenarios characterized by limited historical data or the presence of ambiguous information. Secondly, it introduces a fuzzy chance-constrained programming model, which is aimed at minimizing the project budget while ensuring that the risks associated with cost overruns and schedule delays are confined to specified limits. Thirdly, it advances an enhanced genetic algorithm, integrating an electromagnetism-like mechanism and a scheduling repair process, to improve the efficiency and effectiveness of the optimization process. Findings A real-life street renovation project was analyzed to demonstrate the applicability of the proposed algorithm. The analysis explored three common types of risk preferences: risk-averse, risk-neutral and risk-loving. The results indicate that the proposed algorithm surpasses existing fuzzy repetitive scheduling methods in terms of risk management. It effectively generates schedules that align with the risk preferences of planners and provides worst-case estimates of project performance. Originality/value This research makes a significant contribution to the field by developing a fuzzy chance-constrained programming model and an associated optimization algorithm that is specifically designed for time-cost tradeoffs in repetitive construction projects. A key distinction is that this study considers the risk preferences of planners, which sets it apart from previously developed models. As a result, it provides a practical approach for effective risk management.

Engineering Construction & Architectural ManagementVol. 33(2)
North China Electric Power University (CN)
Industry, innovation and infrastructure
Openalex Percentile: Top 73%
Resource-Constrained Project Scheduling
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.