ENHANCING THE CONTRACTUAL PROVISION FOR SUSPENSION OF WORK IN MALAYSIA: A COMPARATIVE ANALYSIS WITH EMPHASIS ON A CASE STUDY OF GOVERNMENT CONTRACT FORM PWD203A

The government possesses the authority to halt or delay work on-site, either partially or entirely, through the suspension of works as outlined in Clause 50 of the Public Work Department’s PWD203A contract form. However, the global outbreak of the COVID-19 pandemic has revealed the lack of attention towards the proper implementation of work suspension. This study proposes for the improvement of contractual procedures and provisions on the suspension of works of government projects. It addresses the issues pertaining to work suspension in construction projects, examines the existing contract provision in the contract forms, and suggests enhancements of government project contracts. Through a comparative analysis and case study approach focusing on PWD203A, this study identifies the need for establishing clear suspension of work activities, and a fair time restriction mechanism as crucial enhancements to be incorporated into contractual provisions of work suspension. Subsequently, an expert validation process validates the proposed enhancement of the contractual provisions. These findings offer stakeholders valuable insights into practical solutions for more effective management of work suspension of government projects.

Authors

Institutions

Publication Details

Journal
PLANNING MALAYSIA
Published
2024-11-28
DOI
https://doi.org/10.21837/pm.v22i34.1609
Primary Topic
Islamic Finance and Banking Studies
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

ENHANCING THE CONTRACTUAL PROVISION FOR SUSPENSION OF WORK IN MALAYSIA: A COMPARATIVE ANALYSIS WITH EMPHASIS ON A CASE STUDY OF GOVERNMENT CONTRACT FORM PWD203A

Sharifah Mazlina Syed Khuzzan, Mohd Suhaimi Mohd-Danuri, Muhammad Hadi Mustafa, Mazura Mahdzir et al.
PLANNING MALAYSIA
Islamic Finance and Banking Studies
article

ENHANCING THE CONTRACTUAL PROVISION FOR SUSPENSION OF WORK IN MALAYSIA: A COMPARATIVE ANALYSIS WITH EMPHASIS ON A CASE STUDY OF GOVERNMENT CONTRACT FORM PWD203A

Sharifah Mazlina Syed Khuzzan, Mohd Suhaimi Mohd-Danuri, Muhammad Hadi Mustafa, Mazura Mahdzir, Anis Nadhirah Khairul Anuar
article en

Abstract

The government possesses the authority to halt or delay work on-site, either partially or entirely, through the suspension of works as outlined in Clause 50 of the Public Work Department’s PWD203A contract form. However, the global outbreak of the COVID-19 pandemic has revealed the lack of attention towards the proper implementation of work suspension. This study proposes for the improvement of contractual procedures and provisions on the suspension of works of government projects. It addresses the issues pertaining to work suspension in construction projects, examines the existing contract provision in the contract forms, and suggests enhancements of government project contracts. Through a comparative analysis and case study approach focusing on PWD203A, this study identifies the need for establishing clear suspension of work activities, and a fair time restriction mechanism as crucial enhancements to be incorporated into contractual provisions of work suspension. Subsequently, an expert validation process validates the proposed enhancement of the contractual provisions. These findings offer stakeholders valuable insights into practical solutions for more effective management of work suspension of government projects.

PLANNING MALAYSIAVol. 22
University of Malaya (MY), International Islamic University Malaysia (MY)
Openalex Percentile: Top 64%
Islamic Finance and Banking Studies
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

ENHANCING THE CONTRACTUAL PROVISION FOR SUSPENSION OF WORK IN MALAYSIA: A COMPARATIVE ANALYSIS WITH EMPHASIS ON A CASE STUDY OF GOVERNMENT CONTRACT FORM PWD203A — Sharifah Mazlina Syed Khuzzan, Mohd Suhaimi Mohd-Danuri, et al. · PLANNING MALAYSIA (2024) | TGRS Research Map | TGRS