Redundant Constraints Identification Based Acceleration Method for Multi-Stage Robust SCUC Problems

Security constrained unit commitment (SCUC) problem with uncertainty has become an important research task with the increasing scale of renewable energy access in the power system. Multi-stage robust optimization method has been proved to be effective for solving the UC problem with uncertainty, but it has to deal with the difficulty of excessive computation. The complexity of the UC problem is also increasing due to the rapidly expanding overall size of the power system. A common method to improve the efficiency of solving UC problems is to eliminate redundant security constraints. However, this method is mainly applied to the deterministic UC problems at present. In this paper, a solution framework based on a multi-stage robust optimization method with eliminating redundant security constraints is established. Numerical testing is performed for IEEE 24-bus system and 118-bus system. Most of the security constraints are identified as redundant constraints in different scenarios. The computational efficiency is obviously improved after redundant constraints are eliminated.

Authors

Institutions

Publication Details

Published
2024-10-18
DOI
https://doi.org/10.1109/icnsc62968.2024.10760115
Primary Topic
Fault Detection and Control Systems
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Redundant Constraints Identification Based Acceleration Method for Multi-Stage Robust SCUC Problems

Haozhe Li, Wei Qiao, Qiaozhu Zhai, Yuzhou Zhou et al.
Fault Detection and Control Systems
article

Redundant Constraints Identification Based Acceleration Method for Multi-Stage Robust SCUC Problems

Haozhe Li, Wei Qiao, Qiaozhu Zhai, Yuzhou Zhou, Zhijie Han, Yuxuan Zhang
article en

Abstract

Security constrained unit commitment (SCUC) problem with uncertainty has become an important research task with the increasing scale of renewable energy access in the power system. Multi-stage robust optimization method has been proved to be effective for solving the UC problem with uncertainty, but it has to deal with the difficulty of excessive computation. The complexity of the UC problem is also increasing due to the rapidly expanding overall size of the power system. A common method to improve the efficiency of solving UC problems is to eliminate redundant security constraints. However, this method is mainly applied to the deterministic UC problems at present. In this paper, a solution framework based on a multi-stage robust optimization method with eliminating redundant security constraints is established. Numerical testing is performed for IEEE 24-bus system and 118-bus system. Most of the security constraints are identified as redundant constraints in different scenarios. The computational efficiency is obviously improved after redundant constraints are eliminated.

Xi'an Jiaotong University (CN)
Affordable and clean energy
Openalex Percentile: Top 75%
Fault Detection and Control Systems
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.