Assessment of dispute causes in government building maintenance projects through adjusted importance rating and risk mapping

• Causes of disputes in Saudi government building maintenance projects. • Uses FAII and risk mapping to rank dispute causes in maintenance projects. • Identifies top dispute causes: (1) the lack of original as-built drawings, (2) constant government interference, (3) delays in decision-making. • Validates survey findings with real-world case studies to enhance reliability. • Offers insights for authorities to improve contract management and reduce disputes. Despite the reliance of Saudi Arabian government facilities on private contractors for maintenance, there is a persistent rise in disputes between these contractors and government entities. This ongoing issue raises concerns about the efficiency and effectiveness of contract management, ultimately affecting the quality of maintenance services and operational continuity. This study investigates the primary causes of disputes in government building maintenance projects, using both the Frequency Adjusted Importance Index (FAII) and risk mapping methods to analyze and prioritize the causes. A literature review and a designed questionnaire survey were employed to rank dispute causes. Thirty-six responses were analyzed. Cronbach's alpha and coefficient of variation were utilized to assess the collected data's validity and reliability. Three case studies then were utilized as a validation tool, compared against the findings of the survey to integrate practical insights with the theoretical results from the survey. The findings reveal that issues such as (1) the lack of original as-built drawings, (2) constant government interference, (3) delays in decision-making, (4) poorly defined scope of work, and (5) mistakes in bidding or cost estimation are the most critical causes of disputes in these projects. Cross-method validation with real-world case studies further strengthens the reliability of these findings, as these top-ranked causes consistently align with issues encountered in practice. The findings of this study could assist local authorities adopt alternative approaches in managing and executing maintenance contracts, thereby mitigating the causes of disputes.

Authors

Institutions

Publication Details

Journal
Results in Engineering
Published
2024-11-27
DOI
https://doi.org/10.1016/j.rineng.2024.103551
Citations
4
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
1.96
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Assessment of dispute causes in government building maintenance projects through adjusted importance rating and risk mapping

Khwaja Mateen Mazher, Adel Alshaibani, Ali A. Shash, Mouath Masaud Alghamdi
4 citations
Results in Engineering
Construction Project Management and Performance
1.96
article

Assessment of dispute causes in government building maintenance projects through adjusted importance rating and risk mapping

Khwaja Mateen Mazher, Adel Alshaibani, Ali A. Shash, Mouath Masaud Alghamdi
article en
4 citations

Abstract

• Causes of disputes in Saudi government building maintenance projects. • Uses FAII and risk mapping to rank dispute causes in maintenance projects. • Identifies top dispute causes: (1) the lack of original as-built drawings, (2) constant government interference, (3) delays in decision-making. • Validates survey findings with real-world case studies to enhance reliability. • Offers insights for authorities to improve contract management and reduce disputes. Despite the reliance of Saudi Arabian government facilities on private contractors for maintenance, there is a persistent rise in disputes between these contractors and government entities. This ongoing issue raises concerns about the efficiency and effectiveness of contract management, ultimately affecting the quality of maintenance services and operational continuity. This study investigates the primary causes of disputes in government building maintenance projects, using both the Frequency Adjusted Importance Index (FAII) and risk mapping methods to analyze and prioritize the causes. A literature review and a designed questionnaire survey were employed to rank dispute causes. Thirty-six responses were analyzed. Cronbach's alpha and coefficient of variation were utilized to assess the collected data's validity and reliability. Three case studies then were utilized as a validation tool, compared against the findings of the survey to integrate practical insights with the theoretical results from the survey. The findings reveal that issues such as (1) the lack of original as-built drawings, (2) constant government interference, (3) delays in decision-making, (4) poorly defined scope of work, and (5) mistakes in bidding or cost estimation are the most critical causes of disputes in these projects. Cross-method validation with real-world case studies further strengthens the reliability of these findings, as these top-ranked causes consistently align with issues encountered in practice. The findings of this study could assist local authorities adopt alternative approaches in managing and executing maintenance contracts, thereby mitigating the causes of disputes.

Results in EngineeringVol. 24
King Fahd University of Petroleum and Minerals (SA)
Sustainable cities and communities
Openalex Percentile: Top 12%
Construction Project Management and Performance
1.96
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.