Studi Overhaul Aliran Beban PMT GI 150/70 kV Menggunakan Software ETAP pada Jaringan SUTT 70 kV

The power breaker (PMT) in the transmission system functions as a load breaker both under normal circumstances and when a disturbance occurs. In July 2021 it was discovered that there was an SF6 gas leak at (PMT) bay Arjawinangun 2 at Gi Sunyaragi. Under these conditions an overhaul was carried out which in the implementation found several sources of causes of leaks such as scale and corrosion at the joints and packing conditions that were no longer flexible. Before the implementation and after the implementation of the overhoul, tests were carried out including: contact resistance testing, insulation resistance testing and after a series of tests were carried out, then an analysis of the test results was carried out and a voltage drop simulation was carried out using the Etap 12.6 software from a series of activities, 5 simulation results were obtained and concluded that the system is still within safe limits (up 5%, down 10% from the nominal voltage). As well as other tests such as isolation resistance and contact resistance are still included in the specified standard category, so it is concluded that the PMT bay Arjawinangun 2 is in good condition and safe to operate.

Authors

Institutions

Publication Details

Journal
Nucleus Journal
Published
2024-11-10
DOI
https://doi.org/10.32492/nucleus.v3i2.3202
Primary Topic
Electric Power Systems and Control
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Studi Overhaul Aliran Beban PMT GI 150/70 kV Menggunakan Software ETAP pada Jaringan SUTT 70 kV

Mudofar Baehaqi, Agus Siswanto, Mansur Naufal
Nucleus Journal
Electric Power Systems and Control
article

Studi Overhaul Aliran Beban PMT GI 150/70 kV Menggunakan Software ETAP pada Jaringan SUTT 70 kV

Mudofar Baehaqi, Agus Siswanto, Mansur Naufal
article en

Abstract

The power breaker (PMT) in the transmission system functions as a load breaker both under normal circumstances and when a disturbance occurs. In July 2021 it was discovered that there was an SF6 gas leak at (PMT) bay Arjawinangun 2 at Gi Sunyaragi. Under these conditions an overhaul was carried out which in the implementation found several sources of causes of leaks such as scale and corrosion at the joints and packing conditions that were no longer flexible. Before the implementation and after the implementation of the overhoul, tests were carried out including: contact resistance testing, insulation resistance testing and after a series of tests were carried out, then an analysis of the test results was carried out and a voltage drop simulation was carried out using the Etap 12.6 software from a series of activities, 5 simulation results were obtained and concluded that the system is still within safe limits (up 5%, down 10% from the nominal voltage). As well as other tests such as isolation resistance and contact resistance are still included in the specified standard category, so it is concluded that the PMT bay Arjawinangun 2 is in good condition and safe to operate.

Nucleus JournalVol. 3(2)
Universitas Halu Oleo (ID), Universitas 17 Agustus 1945 Cirebon (ID)
Openalex Percentile: Top 81%
Electric Power Systems and Control
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.