Design Change Management using BIM and Autodesk Construction Cloud

Efficient change order management is crucial in construction, particularly as project requirements evolve over time. In Syria's traditional construction process, lengthy gaps between planning, design, and execution significantly increase the likelihood of changes. This paper introduces a methodology that leverages Building Information Modeling (BIM) and cloud computing to enhance change management. A detailed case study of the Al-Eddekhar Housing project in Tartous was conducted, where Revit was employed for 3D modeling and Primavera for scheduling and cost estimation. Changes were meticulously analyzed using Revit's Model Compare tool, tracked through Primavera, and managed using Autodesk Construction Cloud for seamless document exchange and version control. The integration of BIM and cloud computing facilitates real-time collaboration between teams, significantly reducing errors, minimizing delays, and boosting overall project efficiency. The platform also preserves a historical record of project versions, enables visual comparisons of 3D models, and streamlines the approval process for change orders.

Authors

Publication Details

Journal
International Journal of BIM and Engineering Science
Published
2024-11-21
DOI
https://doi.org/10.54216/ijbes.100105
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Design Change Management using BIM and Autodesk Construction Cloud

Lama Saoud, Hiba Hiba
International Journal of BIM and Engineering Science
BIM and Construction Integration
article

Design Change Management using BIM and Autodesk Construction Cloud

Lama Saoud, Hiba Hiba
article en

Abstract

Efficient change order management is crucial in construction, particularly as project requirements evolve over time. In Syria's traditional construction process, lengthy gaps between planning, design, and execution significantly increase the likelihood of changes. This paper introduces a methodology that leverages Building Information Modeling (BIM) and cloud computing to enhance change management. A detailed case study of the Al-Eddekhar Housing project in Tartous was conducted, where Revit was employed for 3D modeling and Primavera for scheduling and cost estimation. Changes were meticulously analyzed using Revit's Model Compare tool, tracked through Primavera, and managed using Autodesk Construction Cloud for seamless document exchange and version control. The integration of BIM and cloud computing facilitates real-time collaboration between teams, significantly reducing errors, minimizing delays, and boosting overall project efficiency. The platform also preserves a historical record of project versions, enables visual comparisons of 3D models, and streamlines the approval process for change orders.

International Journal of BIM and Engineering ScienceVol. 10(1)
Openalex Percentile: Top 78%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Design Change Management using BIM and Autodesk Construction Cloud — Lama Saoud, Hiba Hiba · International Journal of BIM and Engineering Science (2024) | TGRS Research Map | TGRS