Kinerja Waktu Pelaksanaan Proyek Pekerjaan Jalan Di Kabupaten Kolaka Utara (Studi Kasus Jalan Poros Lasusua Desa Totallang)

The aim of the research is to find out or predict how much a project will cost during implementation and to find out the effectiveness of project control using the Earned Value Method. To overcome existing problems, an Earned Value method is used. There are two parameters or indicators used for analysis, namely BCWS, BCWP. Delay deviations can be identified by looking at the Schedule Variance (SV). This method can also be used to determine the efficiency of resource use in the form of the schedule performance index (SPI). The project implementation time aspect has a negative value up to the 12 th week of (SV) -Rp. 44,776,771.84 or schedule performance index (SPI) = 0.82 < 1. The calculation results are obtained from an effectiveness value of 0.85 for controlling project time using the Method Earned Value. In other words, the results of an effectiveness value that is smaller than 1 (one) can be said to be that the Time Performance for the Implementation of the Concrete Pavement Road Work Project in North Kolaka Regency is less effective. From the results of the time performance study using the Earned Value Method, it can be concluded that the Time Performance for the Implementation of the Concrete Pavement Road Work Project in North Kolaka Regency experienced a delay from the initial plan. It is clear that in weeks 1 to 12 the project performance was delayed from the planned schedule

Authors

Institutions

Publication Details

Journal
Sultra Civil Engineering Journal
Published
2024-10-25
DOI
https://doi.org/10.54297/sciej.v5i2.696
Primary Topic
Urban Transport Systems Analysis
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Kinerja Waktu Pelaksanaan Proyek Pekerjaan Jalan Di Kabupaten Kolaka Utara (Studi Kasus Jalan Poros Lasusua Desa Totallang)

Andi Makkawaru, Sufrianto Sufrianto, Vickky Anggara Ilham, La Ode Altakdir Ilahi
Sultra Civil Engineering Journal
Urban Transport Systems Analysis
article

Kinerja Waktu Pelaksanaan Proyek Pekerjaan Jalan Di Kabupaten Kolaka Utara (Studi Kasus Jalan Poros Lasusua Desa Totallang)

Andi Makkawaru, Sufrianto Sufrianto, Vickky Anggara Ilham, La Ode Altakdir Ilahi
article en

Abstract

The aim of the research is to find out or predict how much a project will cost during implementation and to find out the effectiveness of project control using the Earned Value Method. To overcome existing problems, an Earned Value method is used. There are two parameters or indicators used for analysis, namely BCWS, BCWP. Delay deviations can be identified by looking at the Schedule Variance (SV). This method can also be used to determine the efficiency of resource use in the form of the schedule performance index (SPI). The project implementation time aspect has a negative value up to the 12 th week of (SV) -Rp. 44,776,771.84 or schedule performance index (SPI) = 0.82 < 1. The calculation results are obtained from an effectiveness value of 0.85 for controlling project time using the Method Earned Value. In other words, the results of an effectiveness value that is smaller than 1 (one) can be said to be that the Time Performance for the Implementation of the Concrete Pavement Road Work Project in North Kolaka Regency is less effective. From the results of the time performance study using the Earned Value Method, it can be concluded that the Time Performance for the Implementation of the Concrete Pavement Road Work Project in North Kolaka Regency experienced a delay from the initial plan. It is clear that in weeks 1 to 12 the project performance was delayed from the planned schedule

Sultra Civil Engineering JournalVol. 5(2)
Universitas Sulawesi Tenggara (ID)
Decent work and economic growth
Openalex Percentile: Top 76%
Urban Transport Systems Analysis
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.