Identifikasi Added and Non-Value Added activities Melalui Analisis Just In Time Pada Pekerjaan Pondasi Bore Pile

A construction project is a complex job because it involves various resources to achieve the targets of the project. Management of these resources must be carried out with the aim of achieving high productivity. The aim of this research is to determine activities that have added value (Value Added activity) and activities that do not have added value (non-Value Added activity) as well as to evaluate the productivity efficiency of machines and tools in Bore Pile foundation work. The author uses the Just In method Time to identify the effectiveness and efficiency of Bore Pile foundation work. Just In Time will focus on reducing waste so that it can increase productivity. The application of the Just In Time method is only used for resources, namely machines and tools needed for a job. This method will be assisted by the Manufacturing Cycle Effectiveness concept to measure the percentage of Value Added activities. The research results show that there are still several machines or heavy equipment with a percentage of non-Value Added activity that is greater than Value Added activity. This is caused by quite a lot of waiting time and Moving time, resulting in smaller Value Added activity.

Authors

Institutions

Publication Details

Journal
Jurnal Inovasi Konstruksi
Published
2024-10-31
DOI
https://doi.org/10.56911/jik.v3i2.119
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Identifikasi Added and Non-Value Added activities Melalui Analisis Just In Time Pada Pekerjaan Pondasi Bore Pile

Joel M Simanullang
Jurnal Inovasi Konstruksi
Management and Optimization Techniques
article

Identifikasi Added and Non-Value Added activities Melalui Analisis Just In Time Pada Pekerjaan Pondasi Bore Pile

Joel M Simanullang
article en

Abstract

A construction project is a complex job because it involves various resources to achieve the targets of the project. Management of these resources must be carried out with the aim of achieving high productivity. The aim of this research is to determine activities that have added value (Value Added activity) and activities that do not have added value (non-Value Added activity) as well as to evaluate the productivity efficiency of machines and tools in Bore Pile foundation work. The author uses the Just In method Time to identify the effectiveness and efficiency of Bore Pile foundation work. Just In Time will focus on reducing waste so that it can increase productivity. The application of the Just In Time method is only used for resources, namely machines and tools needed for a job. This method will be assisted by the Manufacturing Cycle Effectiveness concept to measure the percentage of Value Added activities. The research results show that there are still several machines or heavy equipment with a percentage of non-Value Added activity that is greater than Value Added activity. This is caused by quite a lot of waiting time and Moving time, resulting in smaller Value Added activity.

Jurnal Inovasi KonstruksiVol. 3(2)
Universitas Gadjah Mada (ID)
Openalex Percentile: Top 64%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Identifikasi Added and Non-Value Added activities Melalui Analisis Just In Time Pada Pekerjaan Pondasi Bore Pile — Joel M Simanullang · Jurnal Inovasi Konstruksi (2024) | TGRS Research Map | TGRS