Reinforcement learning‐based approach for urban road project scheduling considering alternative closure types

Growth in urban population, travel, and motorization continue to cause an increased need for urban projects to expand road capacity. Unfortunately, these projects also cause travel delays, emissions, driver frustration, and other road user adversities. To alleviate these ills, road agencies often face two work zone design choices: close the road fully and re-reroute traffic or implement partial closure. Both options have significant implications for peri-construction road capacity, traveler costs, and the project duration and cost. This study presents a decision-making methodology to facilitate the choice between full road closure and partial closure. The presented decision-making methodology is a bi-level optimization problem: at the upper level, the road agency seeks to optimally schedule road construction work to minimize net vehicle emissions and road construction costs. The lower-level of the problem captures two types of travelers’ route choice behaviors: rational travelers who minimize their travel time and path-loyal travelers who do not change their routes from their pre-construction routes. The bi-level mixed integer nonlinear model is solved using a reinforcement learning-based algorithm (the multi-armed bandit-guided particle swarm optimization [PSO] technique). The computational experiments suggest the superiority of the proposed algorithm, compared to the classic PSO algorithm in terms of solution quality. The numerical results suggest that if the percentage of path-loyal travelers increases, the agency needs to invest more in road project construction to implement under partial closure to avoid a significant increase in vehicle emissions.

Authors

Institutions

Publication Details

Journal
Computer-Aided Civil and Infrastructure Engineering
Published
2024-11-19
DOI
https://doi.org/10.1111/mice.13365
Citations
1
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.27

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Reinforcement learning‐based approach for urban road project scheduling considering alternative closure types

Mohammadhosein Pourgholamali, Mohammad Miralinaghi, Sania E. Seilabi, Samuel Labi et al.
1 citations
Computer-Aided Civil and Infrastructure Engineering
BIM and Construction Integration
0.27
article

Reinforcement learning‐based approach for urban road project scheduling considering alternative closure types

Mohammadhosein Pourgholamali, Mohammad Miralinaghi, Sania E. Seilabi, Samuel Labi, Mostafa Saneii
article en
1 citations

Abstract

Growth in urban population, travel, and motorization continue to cause an increased need for urban projects to expand road capacity. Unfortunately, these projects also cause travel delays, emissions, driver frustration, and other road user adversities. To alleviate these ills, road agencies often face two work zone design choices: close the road fully and re-reroute traffic or implement partial closure. Both options have significant implications for peri-construction road capacity, traveler costs, and the project duration and cost. This study presents a decision-making methodology to facilitate the choice between full road closure and partial closure. The presented decision-making methodology is a bi-level optimization problem: at the upper level, the road agency seeks to optimally schedule road construction work to minimize net vehicle emissions and road construction costs. The lower-level of the problem captures two types of travelers’ route choice behaviors: rational travelers who minimize their travel time and path-loyal travelers who do not change their routes from their pre-construction routes. The bi-level mixed integer nonlinear model is solved using a reinforcement learning-based algorithm (the multi-armed bandit-guided particle swarm optimization [PSO] technique). The computational experiments suggest the superiority of the proposed algorithm, compared to the classic PSO algorithm in terms of solution quality. The numerical results suggest that if the percentage of path-loyal travelers increases, the agency needs to invest more in road project construction to implement under partial closure to avoid a significant increase in vehicle emissions.

Computer-Aided Civil and Infrastructure EngineeringVol. 40(6)
Illinois Institute of Technology (US), University of Toronto (CA), Purdue University West Lafayette (US), University at Buffalo, State University of New York (US)
Stanford Bio-X, Office of Naval Research
Sustainable cities and communities
Openalex Percentile: Top 42%
BIM and Construction Integration
0.27
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.