Navigating Escalation Patterns in Road Construction Projects in Maharashtra

This research delves into the nuanced dynamics of escalation amounts in construction projects, differentiating their implications on residential versus road construction. Detailed analyses of four diverse projects expose distinctive patterns: Project No.1 witnesses peak steel escalation, while material, labour, and POL exhibit constancy. Project No.2 reveals material escalation as dominant, with recuperated steel and cement costs. Conversely, Project No.3 portrays negative escalations for material and POL, dominated by labour impacts. Project No.4 experiences negative escalations attributable to duration shifts. The study unveils a correlation between project duration and escalating costs, highlighting steel, material, and labour as pivotal in residential projects and labour, material, and POL in road projects. The research underscores the critical role of escalation clauses in contracts, elucidating their significance in mitigating direct impacts on project costs. The findings emphasize project-specific factors such as duration, material price fluctuations, project nature, client-contractor dynamics, and governmental policies shaping escalation outcomes.

Authors

Publication Details

Journal
Panamerican mathematical journal.
Published
2024-10-19
DOI
https://doi.org/10.52783/pmj.v34.i4.2027
Primary Topic
Occupational Health and Safety Research
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Navigating Escalation Patterns in Road Construction Projects in Maharashtra

Rahul S. Chaudhari
Panamerican mathematical journal.
Occupational Health and Safety Research
article

Navigating Escalation Patterns in Road Construction Projects in Maharashtra

Rahul S. Chaudhari
article en

Abstract

This research delves into the nuanced dynamics of escalation amounts in construction projects, differentiating their implications on residential versus road construction. Detailed analyses of four diverse projects expose distinctive patterns: Project No.1 witnesses peak steel escalation, while material, labour, and POL exhibit constancy. Project No.2 reveals material escalation as dominant, with recuperated steel and cement costs. Conversely, Project No.3 portrays negative escalations for material and POL, dominated by labour impacts. Project No.4 experiences negative escalations attributable to duration shifts. The study unveils a correlation between project duration and escalating costs, highlighting steel, material, and labour as pivotal in residential projects and labour, material, and POL in road projects. The research underscores the critical role of escalation clauses in contracts, elucidating their significance in mitigating direct impacts on project costs. The findings emphasize project-specific factors such as duration, material price fluctuations, project nature, client-contractor dynamics, and governmental policies shaping escalation outcomes.

Panamerican mathematical journal.Vol. 34(4)
Decent work and economic growth
Openalex Percentile: Top 69%
Occupational Health and Safety Research
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.