Uncertainty reduction in power forecasting of virtual power plant: From day-ahead to balancing markets

Abstract Adjusting prediction data before bidding is a straightforward and cost-effective method to reduce uncertainty and imbalance between bidding data and real-time power supply. To avoid profit loss for virtual power plant, this study proposes an uncertainty optimization model that minimizes the remaining uncertainty after power generation forecasts. The proposed model specifically addresses different weather conditions—rainy, overcast, cloudy, partly cloudy, and sunny—by minimizing the distance between actual and forecasted VPP generation. The model is applied to adjust prediction data of a VPP with an average generation capacity of 1.5 GW in Tokyo, Japan. Bidding data for winter 2024 are predicted using three deep neural network-based methods. The results indicate a significant reduction in both uncertainty and energy storage capacity after using the uncertainty optimization model. Moreover, the findings show that the proposed uncertainty optimization model increases the profit growth rate for prediction methods characterized by high uncertainty.

Authors

Institutions

Publication Details

Journal
Renewable Energy
Published
2024-11-15
DOI
https://doi.org/10.1016/j.renene.2024.121875
Citations
19
Primary Topic
Energy Load and Power Forecasting
Type
article
Field-Weighted Citation Impact
3.96

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Uncertainty reduction in power forecasting of virtual power plant: From day-ahead to balancing markets

Mika Goto, Reza Nadimi
19 citations
Renewable Energy
Energy Load and Power Forecasting
3.96
article

Uncertainty reduction in power forecasting of virtual power plant: From day-ahead to balancing markets

Mika Goto, Reza Nadimi
article en
19 citations

Abstract

Abstract Adjusting prediction data before bidding is a straightforward and cost-effective method to reduce uncertainty and imbalance between bidding data and real-time power supply. To avoid profit loss for virtual power plant, this study proposes an uncertainty optimization model that minimizes the remaining uncertainty after power generation forecasts. The proposed model specifically addresses different weather conditions—rainy, overcast, cloudy, partly cloudy, and sunny—by minimizing the distance between actual and forecasted VPP generation. The model is applied to adjust prediction data of a VPP with an average generation capacity of 1.5 GW in Tokyo, Japan. Bidding data for winter 2024 are predicted using three deep neural network-based methods. The results indicate a significant reduction in both uncertainty and energy storage capacity after using the uncertainty optimization model. Moreover, the findings show that the proposed uncertainty optimization model increases the profit growth rate for prediction methods characterized by high uncertainty.

Renewable EnergyVol. 238
Shibaura Institute of Technology (JP)
Council for Science, Technology and Innovation
Affordable and clean energy
Openalex Percentile: Top 6%
Energy Load and Power Forecasting
3.96
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Uncertainty reduction in power forecasting of virtual power plant: From day-ahead to balancing markets — Mika Goto, Reza Nadimi · Renewable Energy (2024) | TGRS Research Map | TGRS