Improved Building Information Modeling Based Method for Prioritizing Clash Detection in the Building Construction Design Phase

The rising complexity of construction projects and the industry’s commitment to sustainable practices have driven the extensive adoption of Building Information Modeling (BIM) technology. A core function of BIM is the early identification and resolution of clashes during the design phase, which serves to mitigate costly rework and delays in the construction process. This study presents an advanced method for classifying and prioritizing hard clashes between structural components and mechanical, electrical, and plumbing (MEP) systems. Employing the Best-Worst Method (BWM), this research assigned specific weights to structural and MEP elements based on expert evaluations. Six parameters were incorporated into this prioritization framework: the weights determined by the BWM, outputs from Navisworks software (v2021), the ratio of MEP volume to floor volume, the functional purpose of each floor, and the number of adjacent elements. A custom-developed plugin for Autodesk Navisworks integrated these parameters, enabling real-time automated clash prioritization. Clashes were ranked by criticality through a calculation involving the six parameters, which enhanced the efficiency of clash detection by optimizing time and cost considerations during the design phase. Case study results indicate that beams and columns represent the most critical structural elements, while ducts are identified as the most significant MEP elements. The proposed method substantially improves clash detection and prioritization efficiency and accuracy, yielding considerable benefits in project management and resource allocation.

Authors

Institutions

Publication Details

Journal
Buildings
Published
2024-11-13
DOI
https://doi.org/10.3390/buildings14113611
Citations
9
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
2.39
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Improved Building Information Modeling Based Method for Prioritizing Clash Detection in the Building Construction Design Phase

Ali Akbar Shirzadi Javid, Iman Bitaraf, Ali Salimpour, Pedram Elmi
9 citations
Buildings
BIM and Construction Integration
2.39
article

Improved Building Information Modeling Based Method for Prioritizing Clash Detection in the Building Construction Design Phase

Ali Akbar Shirzadi Javid, Iman Bitaraf, Ali Salimpour, Pedram Elmi
article en
9 citations

Abstract

The rising complexity of construction projects and the industry’s commitment to sustainable practices have driven the extensive adoption of Building Information Modeling (BIM) technology. A core function of BIM is the early identification and resolution of clashes during the design phase, which serves to mitigate costly rework and delays in the construction process. This study presents an advanced method for classifying and prioritizing hard clashes between structural components and mechanical, electrical, and plumbing (MEP) systems. Employing the Best-Worst Method (BWM), this research assigned specific weights to structural and MEP elements based on expert evaluations. Six parameters were incorporated into this prioritization framework: the weights determined by the BWM, outputs from Navisworks software (v2021), the ratio of MEP volume to floor volume, the functional purpose of each floor, and the number of adjacent elements. A custom-developed plugin for Autodesk Navisworks integrated these parameters, enabling real-time automated clash prioritization. Clashes were ranked by criticality through a calculation involving the six parameters, which enhanced the efficiency of clash detection by optimizing time and cost considerations during the design phase. Case study results indicate that beams and columns represent the most critical structural elements, while ducts are identified as the most significant MEP elements. The proposed method substantially improves clash detection and prioritization efficiency and accuracy, yielding considerable benefits in project management and resource allocation.

BuildingsVol. 14(11)
Iran University of Science and Technology (IR), K. N. Toosi University of Technology (IR)
Industry, innovation and infrastructure
Openalex Percentile: Top 12%
BIM and Construction Integration
2.39
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Improved Building Information Modeling Based Method for Prioritizing Clash Detection in the Building Construction Design Phase — Ali Akbar Shirzadi Javid, Iman Bitaraf, et al. · Buildings (2024) | TGRS Research Map | TGRS