Analysis of Project Time and Cost using the Crash Program Approach

Project acceleration is a solution to speed up project completion. Project acceleration has various alternatives, including adding overtime hours and adding labor. This research aims to assess the changes in project time and costs following acceleration efforts through options such as increasing working hours (overtime) and adding labor. The project acceleration method used is the crash program method, supported by the Microsoft Project application. The research results show that for the option of adding overtime hours, with 1 hour of overtime, the cost was Rp 27,011,372,606.28 and the duration was 204.13 days; for 2 hours of overtime, the cost increased to Rp 27,156,499,375.32 with a duration of 199.01 days; with 3 hours of overtime, the cost was Rp 27,307,828,821.71 and the duration shortened to 194.62 days; and with 4 hours of overtime, the cost was Rp 27,465,750,984.13 with a duration of 190.92 days. For the alternative of adding labor, under a scenario equivalent to 1 hour of overtime, the cost was Rp 26,846,481,892.32 and the duration was 204.13 days; with 2 hours of overtime, the cost was Rp 26,797,919,204.37 with a duration of 199.01 days; with 3 hours of overtime, the cost decreased to Rp 26,746,499,142.20 and the duration was 194.62 days; and for 4 hours of overtime, the cost was Rp 26,703,236,580.04 with a duration of 190.92 days. Thus, adding labor is identified as an effective alternative due to its economical cost, even though it results in the same project acceleration duration.

Authors

Institutions

Publication Details

Journal
CIVED
Published
2024-09-30
DOI
https://doi.org/10.24036/cived.v11i3.648
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Analysis of Project Time and Cost using the Crash Program Approach

Henny Yustisia, Wido Prasetya Dewanto
CIVED
Construction Project Management and Performance
article

Analysis of Project Time and Cost using the Crash Program Approach

Henny Yustisia, Wido Prasetya Dewanto
article en

Abstract

Project acceleration is a solution to speed up project completion. Project acceleration has various alternatives, including adding overtime hours and adding labor. This research aims to assess the changes in project time and costs following acceleration efforts through options such as increasing working hours (overtime) and adding labor. The project acceleration method used is the crash program method, supported by the Microsoft Project application. The research results show that for the option of adding overtime hours, with 1 hour of overtime, the cost was Rp 27,011,372,606.28 and the duration was 204.13 days; for 2 hours of overtime, the cost increased to Rp 27,156,499,375.32 with a duration of 199.01 days; with 3 hours of overtime, the cost was Rp 27,307,828,821.71 and the duration shortened to 194.62 days; and with 4 hours of overtime, the cost was Rp 27,465,750,984.13 with a duration of 190.92 days. For the alternative of adding labor, under a scenario equivalent to 1 hour of overtime, the cost was Rp 26,846,481,892.32 and the duration was 204.13 days; with 2 hours of overtime, the cost was Rp 26,797,919,204.37 with a duration of 199.01 days; with 3 hours of overtime, the cost decreased to Rp 26,746,499,142.20 and the duration was 194.62 days; and for 4 hours of overtime, the cost was Rp 26,703,236,580.04 with a duration of 190.92 days. Thus, adding labor is identified as an effective alternative due to its economical cost, even though it results in the same project acceleration duration.

CIVEDVol. 11(3)
State University of Padang (ID)
Decent work and economic growth
Openalex Percentile: Top 75%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Analysis of Project Time and Cost using the Crash Program Approach — Henny Yustisia, Wido Prasetya Dewanto · CIVED (2024) | TGRS Research Map | TGRS