Technology development of advanced dual fluidized bed steam gasification from pilot to demonstration scale – First results from a newly commissioned 1 MW demonstration plant

• Description of first operation a 1 MW demonstration scale advanced dual fluidised bed plant. • Comparison with results from 100 kW pilot scale. • Detailed mass and energy balances and fluid dynamics investigation to compare scalability of process design. • Recommendations for future process optimisation. The advanced dual fluidized bed steam gasification technology allows the generation of a medium-calorific product gas from various feedstocks. Thereby, biogenic residues, municipal and industrial wastes e.g., sewage sludge or rejects from pulp and paper industry can be utilised. This paper presents the development step of this technology from pilot to demonstration plant scale i.e. the step from technology readiness level 4 to 6. The newly erected demonstration plant at the Syngas Platform Vienna is designed for 1 MW th fuel input power and incorporates a counter current column as the upper part of the gasification. This design choice already resulted in an improvement of product gas quality in pilot scale. By comparing the data gathered from multiple years of 100 kW th pilot scale testing at TU Wien with first results from the new demonstration plant via mass and energy balance simulation, fluidisation regimes and temperature and pressure profiles, the success of the scale-up of the reactor design is proven. The first full load operation achieved a conversion of 1 MW fuel input power into 769 kW product gas power. This translates to 256 kg/h dry biomass being converted into 245 Nm 3 /h of dry product gas. Although first experiments with the reference feedstock high-grade wood chips showed good reproducibility of the results achieved in pilot scale, challenges still remain. The expected product gas composition was different compared to pilot scale results, as the volume share of hydrogen was lower and the relative content of carbon monoxide and carbon dioxide inverted. While the results show an important intermediate step in the process development, the challenges of improving product gas quality and increasing overall conversion efficiency remain to be tackled.

Authors

Institutions

Publication Details

Journal
Fuel
Published
2024-11-11
DOI
https://doi.org/10.1016/j.fuel.2024.133376
Citations
10
Primary Topic
Thermochemical Biomass Conversion Processes
Type
article
Field-Weighted Citation Impact
1.84
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Technology development of advanced dual fluidized bed steam gasification from pilot to demonstration scale – First results from a newly commissioned 1 MW demonstration plant

Miriam Huber, Hermann Hofbauer, Katharina Fürsatz, Florian Benedikt et al.
10 citations
Fuel
Thermochemical Biomass Conversion Processes
1.84
article

Technology development of advanced dual fluidized bed steam gasification from pilot to demonstration scale – First results from a newly commissioned 1 MW demonstration plant

Miriam Huber, Hermann Hofbauer, Katharina Fürsatz, Florian Benedikt, Johannes C. Schmid, David Kadlez, Stefan Müller
article en
10 citations

Abstract

• Description of first operation a 1 MW demonstration scale advanced dual fluidised bed plant. • Comparison with results from 100 kW pilot scale. • Detailed mass and energy balances and fluid dynamics investigation to compare scalability of process design. • Recommendations for future process optimisation. The advanced dual fluidized bed steam gasification technology allows the generation of a medium-calorific product gas from various feedstocks. Thereby, biogenic residues, municipal and industrial wastes e.g., sewage sludge or rejects from pulp and paper industry can be utilised. This paper presents the development step of this technology from pilot to demonstration plant scale i.e. the step from technology readiness level 4 to 6. The newly erected demonstration plant at the Syngas Platform Vienna is designed for 1 MW th fuel input power and incorporates a counter current column as the upper part of the gasification. This design choice already resulted in an improvement of product gas quality in pilot scale. By comparing the data gathered from multiple years of 100 kW th pilot scale testing at TU Wien with first results from the new demonstration plant via mass and energy balance simulation, fluidisation regimes and temperature and pressure profiles, the success of the scale-up of the reactor design is proven. The first full load operation achieved a conversion of 1 MW fuel input power into 769 kW product gas power. This translates to 256 kg/h dry biomass being converted into 245 Nm 3 /h of dry product gas. Although first experiments with the reference feedstock high-grade wood chips showed good reproducibility of the results achieved in pilot scale, challenges still remain. The expected product gas composition was different compared to pilot scale results, as the volume share of hydrogen was lower and the relative content of carbon monoxide and carbon dioxide inverted. While the results show an important intermediate step in the process development, the challenges of improving product gas quality and increasing overall conversion efficiency remain to be tackled.

FuelVol. 381
TU Wien (AT), BEST - Bioenergy and Sustainable Technologies (Austria) (AT), Umeå University (SE), BOKU University (AT)
Openalex Percentile: Top 15%
Thermochemical Biomass Conversion Processes
1.84
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.