Considering Daily Maintenance Schedule Under Uncertainty in Hydro-Thermal Operation Planning for Reserve Margin Calculation

This paper presents a proposal to analyze the impact of considering a programmed power plants maintenance schedule at operation planning, instead of applying historical average unavailability, in order to optimize the reserve margin. For that purpose, a Mixed Integer Programming model is implemented to yield a schedule that targets system reliability by maximizing the Conditional Value at Risk of the days with worst power reserve margin. To incorporate uncertainties inherent to the actual maintenance realization, this study includes a probabilistic approach to represent delays on the starting date and duration of the programmed maintenance.

Authors

Institutions

Publication Details

Published
2024-09-16
DOI
https://doi.org/10.1109/isap63260.2024.10744198
Primary Topic
Reservoir Engineering and Simulation Methods
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Considering Daily Maintenance Schedule Under Uncertainty in Hydro-Thermal Operation Planning for Reserve Margin Calculation

Carmen L.T. Borges, Tiago P. C. de Andrade, Rodrigo Benoliel, C. C. Luiz
Reservoir Engineering and Simulation Methods
article

Considering Daily Maintenance Schedule Under Uncertainty in Hydro-Thermal Operation Planning for Reserve Margin Calculation

Carmen L.T. Borges, Tiago P. C. de Andrade, Rodrigo Benoliel, C. C. Luiz
article en

Abstract

This paper presents a proposal to analyze the impact of considering a programmed power plants maintenance schedule at operation planning, instead of applying historical average unavailability, in order to optimize the reserve margin. For that purpose, a Mixed Integer Programming model is implemented to yield a schedule that targets system reliability by maximizing the Conditional Value at Risk of the days with worst power reserve margin. To incorporate uncertainties inherent to the actual maintenance realization, this study includes a probabilistic approach to represent delays on the starting date and duration of the programmed maintenance.

Universidade Federal do Rio de Janeiro (BR)
Climate action
Openalex Percentile: Top 73%
Reservoir Engineering and Simulation Methods
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Considering Daily Maintenance Schedule Under Uncertainty in Hydro-Thermal Operation Planning for Reserve Margin Calculation — Carmen L.T. Borges, Tiago P. C. de Andrade, et al. · (2024) | TGRS Research Map | TGRS