Potential risk factors affecting cost and schedule performance in the case of construction projects in Dire Dawa city administration and Harari region, Ethiopia

Construction projects are inherently fragmented and complex, influenced by various risk factors that can significantly affect both costs and schedules. Identifying and prioritizing these risk factors is crucial for enhancing project management and achieving successful outcomes. This research aimed to identify the most significant risk factors affecting construction projects in terms of cost and schedule performance within the Dire Dawa City Administration and Harari Region, considering the perspectives of contractors, clients, and consultants to provide actionable insights for risk mitigation. A comprehensive literature review and pilot survey initially identified 41 risk factors, which were refined through an iterative process to select 42 factors for a detailed questionnaire survey. Additionally, semi-structured interviews were conducted to gather qualitative insights. Data analysis employed mean ratings to identify the top ten risk factors, utilizing Probability Impact (P-I) Matrix and regression techniques to assess each factor’s significance. The results highlighted six critical risk factors among the ten identified as most impactful: inflation, increases in material prices, exchange rate fluctuations, payment delays, poorly coordinated design, and material delays. The findings indicated strong positive correlation values (R = 0.800 and R = 0.840) in both models, suggesting that as one variable increases, the other tends to increase as well. These insights provide valuable guidance for project managers, emphasizing the need to focus on these critical risk factors to improve cost and schedule management, ultimately enhancing project outcomes and minimizing cost overruns in the region.

Authors

Institutions

Publication Details

Journal
Building Engineering
Published
2024-11-08
DOI
https://doi.org/10.59400/be1509
Primary Topic
Construction Project Management and Performance
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Potential risk factors affecting cost and schedule performance in the case of construction projects in Dire Dawa city administration and Harari region, Ethiopia

Mohammadzen Hasan Darsa, Yonatan Getachew Zegeye
Building Engineering
Construction Project Management and Performance
article

Potential risk factors affecting cost and schedule performance in the case of construction projects in Dire Dawa city administration and Harari region, Ethiopia

Mohammadzen Hasan Darsa, Yonatan Getachew Zegeye
article en

Abstract

Construction projects are inherently fragmented and complex, influenced by various risk factors that can significantly affect both costs and schedules. Identifying and prioritizing these risk factors is crucial for enhancing project management and achieving successful outcomes. This research aimed to identify the most significant risk factors affecting construction projects in terms of cost and schedule performance within the Dire Dawa City Administration and Harari Region, considering the perspectives of contractors, clients, and consultants to provide actionable insights for risk mitigation. A comprehensive literature review and pilot survey initially identified 41 risk factors, which were refined through an iterative process to select 42 factors for a detailed questionnaire survey. Additionally, semi-structured interviews were conducted to gather qualitative insights. Data analysis employed mean ratings to identify the top ten risk factors, utilizing Probability Impact (P-I) Matrix and regression techniques to assess each factor’s significance. The results highlighted six critical risk factors among the ten identified as most impactful: inflation, increases in material prices, exchange rate fluctuations, payment delays, poorly coordinated design, and material delays. The findings indicated strong positive correlation values (R = 0.800 and R = 0.840) in both models, suggesting that as one variable increases, the other tends to increase as well. These insights provide valuable guidance for project managers, emphasizing the need to focus on these critical risk factors to improve cost and schedule management, ultimately enhancing project outcomes and minimizing cost overruns in the region.

Building EngineeringVol. 3(1)
Dire Dawa University (ET)
Openalex Percentile: Top 76%
Construction Project Management and Performance
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.