A hybrid metaheuristic and simulation approach towards green project scheduling

Abstract This research tackles the environmental concern of greenhouse gas emissions in the execution of projects, with a focus on multi-site projects where the transportation of resources is a major source of emissions. Despite growing consciousness among consumers and stakeholders about sustainability, the domain of project scheduling has often overlooked the environmental impact. This paper seeks to bridge this oversight by exploring how to reduce greenhouse gas emissions during both project activities and resource transportation. A novel approach is proposed, combining a simulation model with an improved non-dominated sorted genetic algorithm. The simulation model incorporates the stochastic nature of emission rates and costs. This method is further refined with innovative techniques such as magnet-based crossover and mode reassignment. The former is a genetic algorithm operation inspired by magnetic attraction, which allows for a more diverse and effective exploration of solutions by aligning similar ’genes’ from parent solutions. The latter is a strategy for reallocating resources during project execution to optimize efficiency and reduce emissions. The efficacy of the proposed method is validated through testing on 2810 scenarios from established benchmark libraries, 100 additional scenarios adhering to the conventional multi-site problems, and a case study. The Best-Worst Method (BWM) is applied for identifying the best solution. The findings indicate substantial enhancements compared to traditional methods with a 12.7% decrease in project duration, 11.4% in costs, and a remarkable 13.6% reduction in greenhouse gas emissions.

Authors

Institutions

Publication Details

Journal
Annals of Operations Research
Published
2024-11-06
DOI
https://doi.org/10.1007/s10479-024-06291-z
Citations
8
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
3.92
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

A hybrid metaheuristic and simulation approach towards green project scheduling

Mahshid Tootoonchy, Seyed Mojtaba Sajadi, Rahmat Rabet
8 citations
Annals of Operations Research
Resource-Constrained Project Scheduling
3.92
article

A hybrid metaheuristic and simulation approach towards green project scheduling

Mahshid Tootoonchy, Seyed Mojtaba Sajadi, Rahmat Rabet
article en
8 citations

Abstract

Abstract This research tackles the environmental concern of greenhouse gas emissions in the execution of projects, with a focus on multi-site projects where the transportation of resources is a major source of emissions. Despite growing consciousness among consumers and stakeholders about sustainability, the domain of project scheduling has often overlooked the environmental impact. This paper seeks to bridge this oversight by exploring how to reduce greenhouse gas emissions during both project activities and resource transportation. A novel approach is proposed, combining a simulation model with an improved non-dominated sorted genetic algorithm. The simulation model incorporates the stochastic nature of emission rates and costs. This method is further refined with innovative techniques such as magnet-based crossover and mode reassignment. The former is a genetic algorithm operation inspired by magnetic attraction, which allows for a more diverse and effective exploration of solutions by aligning similar ’genes’ from parent solutions. The latter is a strategy for reallocating resources during project execution to optimize efficiency and reduce emissions. The efficacy of the proposed method is validated through testing on 2810 scenarios from established benchmark libraries, 100 additional scenarios adhering to the conventional multi-site problems, and a case study. The Best-Worst Method (BWM) is applied for identifying the best solution. The findings indicate substantial enhancements compared to traditional methods with a 12.7% decrease in project duration, 11.4% in costs, and a remarkable 13.6% reduction in greenhouse gas emissions.

Annals of Operations Research
The University of Sydney (AU), Islamic Azad University, Science and Research Branch (IR), Aston University (GB)
Responsible consumption and production
Openalex Percentile: Top 6%
Resource-Constrained Project Scheduling
3.92
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

A hybrid metaheuristic and simulation approach towards green project scheduling — Mahshid Tootoonchy, Seyed Mojtaba Sajadi, et al. · Annals of Operations Research (2024) | TGRS Research Map | TGRS