Operation of Flushing Gate on Sediment Flushing Efficiency: A Case Study of Alale Weir

This study discuss about hydraulic physical model tests of Alale weir to ensure hydraulic flow behaviour of design flood, condition on downstream of weir, and sediment flushing. In this study, observation were made on a physical hydraulic model in the laboratory with a scale of 1 : 50. Flushing tests were carried out to determine effectivity of the flushing, condition of sedimentation or scouring that occurred at downstream. Alale Weir has 3 flushing gate on the right side of the weir. Flushing is carried out using discharge Q25yr with a flowing duration of 1 hour. Flushing gate has considered quite effective in flushing sediment from upstream of weir. The sediment carried is almost 50% in all flushing scenarios. 6th flushing scenario (gate 1 and 2 were closed and gate 3 was fully opened) has the highest efficiency, 53.81%.

Authors

Institutions

Publication Details

Journal
MEDIA KOMUNIKASI TEKNIK SIPIL
Published
2024-09-19
DOI
https://doi.org/10.14710/mkts.v30i1.60651
Primary Topic
Hydraulic flow and structures
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Operation of Flushing Gate on Sediment Flushing Efficiency: A Case Study of Alale Weir

Evi Nur Cahya, Nur Sholawatini, Very Dermawan, Muhammad Nurjati Hidayat
MEDIA KOMUNIKASI TEKNIK SIPIL
Hydraulic flow and structures
article

Operation of Flushing Gate on Sediment Flushing Efficiency: A Case Study of Alale Weir

Evi Nur Cahya, Nur Sholawatini, Very Dermawan, Muhammad Nurjati Hidayat
article en

Abstract

This study discuss about hydraulic physical model tests of Alale weir to ensure hydraulic flow behaviour of design flood, condition on downstream of weir, and sediment flushing. In this study, observation were made on a physical hydraulic model in the laboratory with a scale of 1 : 50. Flushing tests were carried out to determine effectivity of the flushing, condition of sedimentation or scouring that occurred at downstream. Alale Weir has 3 flushing gate on the right side of the weir. Flushing is carried out using discharge Q25yr with a flowing duration of 1 hour. Flushing gate has considered quite effective in flushing sediment from upstream of weir. The sediment carried is almost 50% in all flushing scenarios. 6th flushing scenario (gate 1 and 2 were closed and gate 3 was fully opened) has the highest efficiency, 53.81%.

MEDIA KOMUNIKASI TEKNIK SIPILVol. 30(1)
University of Brawijaya (ID)
Openalex Percentile: Top 78%
Hydraulic flow and structures
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Operation of Flushing Gate on Sediment Flushing Efficiency: A Case Study of Alale Weir — Evi Nur Cahya, Nur Sholawatini, et al. · MEDIA KOMUNIKASI TEKNIK SIPIL (2024) | TGRS Research Map | TGRS