Automatic selection of the best performing control point approach for project control with resource constraints

During project execution, the actual project progress shows deviations from the baseline schedule due to uncertainty. To complete the project timely, project monitoring is performed at discrete control points to identify project opportunities/problems and take possible corrective actions. These control points affect the quality of project monitoring and corrective actions, but little guidance is available on identifying situations where the control points pay off the most in terms of project duration. This paper proposes new control point approaches considering the risk, the complexity of the network, and subnetwork information to determine the timing of project monitoring and action taking. Moreover, new parameters are proposed to model more realistic project characteristics. Subsequently, a classification model is developed to select the best performing control point approach given project characteristics. An extensive computational experiment is conducted on a set of 3,810 artificial projects with diverse project characteristics to evaluate the performance of the classification model and further validate it on empirical project data. The computational results indicate that the classification model outperforms the average performance of any proposed control point approaches. The results also show that the resource variability that indicates the resource usage deviations between project activities is the primary driver for detecting the best control point approach for projects with resource constraints. • The risk, network, and subnetwork control point approaches are proposed. • New project parameters are introduced to model realistic project features. • A classification model is built to select the best approach given project features. • The classification model outperforms any single proposed control point approach. • Resource variability is the main driver for detecting the best approach.

Authors

Institutions

Publication Details

Journal
European Journal of Operational Research
Published
2024-11-04
DOI
https://doi.org/10.1016/j.ejor.2024.10.025
Citations
2
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
0.98

Funders

Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Automatic selection of the best performing control point approach for project control with resource constraints

Jinbo Song, Mario Vanhoucke, Jie Song
2 citations
European Journal of Operational Research
Resource-Constrained Project Scheduling
0.98
article

Automatic selection of the best performing control point approach for project control with resource constraints

Jinbo Song, Mario Vanhoucke, Jie Song
article en
2 citations

Abstract

During project execution, the actual project progress shows deviations from the baseline schedule due to uncertainty. To complete the project timely, project monitoring is performed at discrete control points to identify project opportunities/problems and take possible corrective actions. These control points affect the quality of project monitoring and corrective actions, but little guidance is available on identifying situations where the control points pay off the most in terms of project duration. This paper proposes new control point approaches considering the risk, the complexity of the network, and subnetwork information to determine the timing of project monitoring and action taking. Moreover, new parameters are proposed to model more realistic project characteristics. Subsequently, a classification model is developed to select the best performing control point approach given project characteristics. An extensive computational experiment is conducted on a set of 3,810 artificial projects with diverse project characteristics to evaluate the performance of the classification model and further validate it on empirical project data. The computational results indicate that the classification model outperforms the average performance of any proposed control point approaches. The results also show that the resource variability that indicates the resource usage deviations between project activities is the primary driver for detecting the best control point approach for projects with resource constraints. • The risk, network, and subnetwork control point approaches are proposed. • New project parameters are introduced to model realistic project features. • A classification model is built to select the best approach given project features. • The classification model outperforms any single proposed control point approach. • Resource variability is the main driver for detecting the best approach.

European Journal of Operational ResearchVol. 322(1)
Dalian University of Technology (CN), Ghent University (BE), Dalian University (CN), Vlerick Business School (BE), University College London (GB)
National Natural Science Foundation of China, National Office for Philosophy and Social Sciences, National Social Science Fund of China
Openalex Percentile: Top 20%
Resource-Constrained Project Scheduling
0.98
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.