Heuristic approaches for a multi-mode resource availability cost problem in aircraft manufacturing

• A time-constrained project scheduling problem in aircraft manufacturing is studied. • Generalized temporal constraints and a multi-mode situation are considered • A priority rule-based heuristic and a biased random-key genetic algorithm are designed. • Problem instances motivated by settings found at a large aircraft manufacturer are used. • Computational experiments demonstrate that the genetic algorithm performs well. A multi-mode time-constrained project scheduling problem with generalized temporal constraints arising in aircraft manufacturing is studied in the paper. We propose a priority rule-based heuristic (PRH) and a biased random-key genetic algorithm (BRKGA) for its solution. A serial generation scheme (SGS) is used for computing schedules from a priority order of the tasks with given resource capacities and mode assignments. The SGS cannot guarantee that the maximum project duration and maximum time lags are respected. Starting with the highest possible resource capacities, the PRH performs the SGS in a repeated manner, reducing the least used resource capacity by one unit until the schedule becomes infeasible. Different priority rules are used for determining both mode assignments and task priority orders. We encode these two decisions as well as the resource capacities in the BRKGA and apply the SGS for decoding. Project duration and maximum time lag violations are penalized in the fitness function. Extensive computational experiments based on problem instances motivated by settings found at a large aircraft manufacturer demonstrate that the BRKGA outperforms the PRH under almost all experimental conditions, especially for problem instances with more complex networks and shorter maximum project durations.

Authors

Institutions

Publication Details

Journal
Computers & Operations Research
Published
2024-11-03
DOI
https://doi.org/10.1016/j.cor.2024.106888
Citations
4
Primary Topic
Resource-Constrained Project Scheduling
Type
article
Field-Weighted Citation Impact
1.96
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Heuristic approaches for a multi-mode resource availability cost problem in aircraft manufacturing

Alexander Biele, Lars Mönch, Jan Bierbüße
4 citations
Computers & Operations Research
Resource-Constrained Project Scheduling
1.96
article

Heuristic approaches for a multi-mode resource availability cost problem in aircraft manufacturing

Alexander Biele, Lars Mönch, Jan Bierbüße
article en
4 citations

Abstract

• A time-constrained project scheduling problem in aircraft manufacturing is studied. • Generalized temporal constraints and a multi-mode situation are considered • A priority rule-based heuristic and a biased random-key genetic algorithm are designed. • Problem instances motivated by settings found at a large aircraft manufacturer are used. • Computational experiments demonstrate that the genetic algorithm performs well. A multi-mode time-constrained project scheduling problem with generalized temporal constraints arising in aircraft manufacturing is studied in the paper. We propose a priority rule-based heuristic (PRH) and a biased random-key genetic algorithm (BRKGA) for its solution. A serial generation scheme (SGS) is used for computing schedules from a priority order of the tasks with given resource capacities and mode assignments. The SGS cannot guarantee that the maximum project duration and maximum time lags are respected. Starting with the highest possible resource capacities, the PRH performs the SGS in a repeated manner, reducing the least used resource capacity by one unit until the schedule becomes infeasible. Different priority rules are used for determining both mode assignments and task priority orders. We encode these two decisions as well as the resource capacities in the BRKGA and apply the SGS for decoding. Project duration and maximum time lag violations are penalized in the fitness function. Extensive computational experiments based on problem instances motivated by settings found at a large aircraft manufacturer demonstrate that the BRKGA outperforms the PRH under almost all experimental conditions, especially for problem instances with more complex networks and shorter maximum project durations.

Computers & Operations ResearchVol. 176
FernUniversität in Hagen (DE), Airbus (India) (IN), Airbus (Germany) (DE)
Decent work and economic growth
Openalex Percentile: Top 12%
Resource-Constrained Project Scheduling
1.96
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.

Heuristic approaches for a multi-mode resource availability cost problem in aircraft manufacturing — Alexander Biele, Lars Mönch, et al. · Computers & Operations Research (2024) | TGRS Research Map | TGRS