PENERAPAN CRITICAL PATH METHOD DALAM PENJADWALAN PROYEK PEMASANGAN TANGKI STORAGE ST-1812, STUDI KASUS PADA PT. MSM

The installation of the ST-1812 storage tank aims to improve production efficiency at PT. MSM by saving costs in the use of steam from 16 hours to only 4 hours, which is used to heat the final product to temperature of 63°C according to work instructions. Critical Path Method is used to determine the optimal construction time, because this method can identify the sequence of tasks that are most critical or that have the most impact on the duration of the entire project. The purpose of this study is to determine the optimal duration for implementation and completion of the ST-1812 storage tank installation project at PT MSM. The analysis of the CPM application showed that the project took 90 days to complete, with 19 activities included in the critical path. The addition of working hours (overtime) on activities on the critical path makes the project can be completed in 73 days, 17 days faster than the initial duration of the project. The initial cost of the project was IDR 66,555,000, and the cost after accelerating the project with crashing calculations was IDR 74,886,429, with a cost slope of IDR 8,331,429.

Authors

Institutions

Publication Details

Journal
Jurnal Ilmiah Teknik Industri
Published
2024-10-25
DOI
https://doi.org/10.24912/jitiuntar.v12i2.31706
Primary Topic
Management and Optimization Techniques
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

PENERAPAN CRITICAL PATH METHOD DALAM PENJADWALAN PROYEK PEMASANGAN TANGKI STORAGE ST-1812, STUDI KASUS PADA PT. MSM

Dwi Noviarsi Patria Nugraha, Manik Ayu Titisari
Jurnal Ilmiah Teknik Industri
Management and Optimization Techniques
article

PENERAPAN CRITICAL PATH METHOD DALAM PENJADWALAN PROYEK PEMASANGAN TANGKI STORAGE ST-1812, STUDI KASUS PADA PT. MSM

Dwi Noviarsi Patria Nugraha, Manik Ayu Titisari
article en

Abstract

The installation of the ST-1812 storage tank aims to improve production efficiency at PT. MSM by saving costs in the use of steam from 16 hours to only 4 hours, which is used to heat the final product to temperature of 63°C according to work instructions. Critical Path Method is used to determine the optimal construction time, because this method can identify the sequence of tasks that are most critical or that have the most impact on the duration of the entire project. The purpose of this study is to determine the optimal duration for implementation and completion of the ST-1812 storage tank installation project at PT MSM. The analysis of the CPM application showed that the project took 90 days to complete, with 19 activities included in the critical path. The addition of working hours (overtime) on activities on the critical path makes the project can be completed in 73 days, 17 days faster than the initial duration of the project. The initial cost of the project was IDR 66,555,000, and the cost after accelerating the project with crashing calculations was IDR 74,886,429, with a cost slope of IDR 8,331,429.

Jurnal Ilmiah Teknik IndustriVol. 12(2)
Universitas PGRI Semarang (ID), Universitas PGRI Adi Buana Surabaya
Affordable and clean energy
Openalex Percentile: Top 67%
Management and Optimization Techniques
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.