Application of Earned Value Analysis Method and Earned Schedule Method to Time and Cost Control In Bank X Building Project

Construction projects are activities that must be completed within limited time and resources. This research aims to identify risky activities and make control efforts to reduce the level of hazard risk in the installation of steel box girder on the bridge. This research used a mixed methods approach, combining quantitative and qualitative methods. Data were collected through surveys and interviews with 60 respondents from 35 bridge projects. The results showed that there were 29 variables of work accident risk factors, including 3 variables with moderate risk levels, 24 variables with high risk levels, and 2 variables with extreme risk levels. The highest risk factors were mobilization that caused congestion and crane overturning during girder lifting that caused operators to fall. To reduce the risk level, efforts are made to ensure all work is done correctly, conduct regular safety inspections, and ensure an effective communication system in the installation of steel box girders on the bridge. The findings can serve as a basis for policy makers to develop better OHS regulations and guidelines, as well as provide valuable information for the development of more effective safety training programs for workers in the construction sector.

Authors

Institutions

Publication Details

Journal
Jurnal Syntax Transformation
Published
2024-10-20
DOI
https://doi.org/10.46799/jst.v5i10.988
Primary Topic
BIM and Construction Integration
Type
article
Field-Weighted Citation Impact
0.00
Controls
|||
ALL TIME
JAN
FEB
MAR
APR
MAY
JUN
JUL
AUG
SEP
OCT
article

Application of Earned Value Analysis Method and Earned Schedule Method to Time and Cost Control In Bank X Building Project

M. Silman, Dina Afrila, Egi Reksa Gumelar, Aryati Indah Kusumastuti
Jurnal Syntax Transformation
BIM and Construction Integration
article

Application of Earned Value Analysis Method and Earned Schedule Method to Time and Cost Control In Bank X Building Project

M. Silman, Dina Afrila, Egi Reksa Gumelar, Aryati Indah Kusumastuti
article en

Abstract

Construction projects are activities that must be completed within limited time and resources. This research aims to identify risky activities and make control efforts to reduce the level of hazard risk in the installation of steel box girder on the bridge. This research used a mixed methods approach, combining quantitative and qualitative methods. Data were collected through surveys and interviews with 60 respondents from 35 bridge projects. The results showed that there were 29 variables of work accident risk factors, including 3 variables with moderate risk levels, 24 variables with high risk levels, and 2 variables with extreme risk levels. The highest risk factors were mobilization that caused congestion and crane overturning during girder lifting that caused operators to fall. To reduce the risk level, efforts are made to ensure all work is done correctly, conduct regular safety inspections, and ensure an effective communication system in the installation of steel box girders on the bridge. The findings can serve as a basis for policy makers to develop better OHS regulations and guidelines, as well as provide valuable information for the development of more effective safety training programs for workers in the construction sector.

Jurnal Syntax TransformationVol. 5(10)
Universitas Swadaya Gunung Jati (ID)
Openalex Percentile: Top 80%
BIM and Construction Integration
AI Navigator

Ask Laika to Summarize, Analyze, and Connect papers live on the map.

Summarize Papers & Methodologies

Extract key findings, datasets, and comparative methods across publications.

Benchmark Rankings & Visual Analytics

Rank top research institutions, authors, funders, topics, and journals by Field-Weighted Citation Impact (FWCI) and paper volume with instant charts.

Connect Distant Disciplines

Bridge topological clusters on the map to find hidden collaborative intersections.